Answer / a. nagaraja
Refractory work will be done in the boiler at the bottom
four sides, manhole doors,burner area, peephole area and at
the top of the boiler. To heat the refractory from low
temp. to high temp, slow firing is done. So that
refractory will be gripped. And also to remove the
unwanted particles like sand, rust, oil and others from
boiler tubes and headers slow firing is done.
TSP and NaoH chemicals will be added with D.M water and it
will be filled in the boiler. The prs. will raise slowly
up to max. 15kg/sq.cm
| Is This Answer Correct ? | 21 Yes | 3 No |
How can we calculate the per hour productivity of a hydraulic rock breaker,for excavator..
Define reynolds number [re].
In auto mobile industry for any type of vehicle how can we differentiate 2 stroke and 4 stroke engine....
in which condition turbine bearing vibration high
Have you been a team leader in your previous or present job and what are the challenges of associated with team leadership?
0 Answers Cree Construction Development,
Hydrogen cannot be removed easily from molten steel. What harm hydrogen has on property of steel ?
What is FEED?
What is the difference between machine and machine tool?
Why do you want to work at our company
I want technical questions of previous reqruitment examination
what do you mean by resistivity survey of tubewell
What is the mathed of maintain oxizen level in a air tite A/c room.
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)