How to Calculate Contracted Maximum demand using motor Hp or
Current

Answers were Sorted based on User's Feedback



How to Calculate Contracted Maximum demand using motor Hp or Current..

Answer / k.prakashchandra

Max contract demand (MD) is in KVA

Is This Answer Correct ?    8 Yes 2 No

How to Calculate Contracted Maximum demand using motor Hp or Current..

Answer / j.srirami reddi

SUPPOSE THE RUNNING LOAD IS 116 KW THE THE MAXIMUM DEMAND
WILL BE 145 KVA.
KVA=KW/PF. CONSIDERING THE POWER FACTOR AS 0.8. THAN THE KVA
= 116/0.8= 145 KVA

Is This Answer Correct ?    7 Yes 3 No

How to Calculate Contracted Maximum demand using motor Hp or Current..

Answer / manoj

The maximum demand using motor hp or current is found by
calculating the full load current of each motor considering
power factor to be 0.8.Suppose ten motors are connected in
a circuit,the maximum demand can be found by adding the
individual full load current of each motor

Is This Answer Correct ?    7 Yes 4 No

Post New Answer

More Electrical Engineering Interview Questions

Is it possible to power factor more than unity?

9 Answers   BEL,


In case of salient pole alternator when number of poles are 4 or more than 4 it helps the flux wave to be sinusoid as air gap length is increased from center to tip , but if the number of poles are 2 how does the flux wave is sinusoidal?

0 Answers  


For a 50MVA (138/69/13.8 KV) transformer, what would be the maximum demand in order not to exceed 80% of its operating capacity.

2 Answers  


if we convert watt into kva,which one formula use by us,pls tell me?

16 Answers   ABB,


how to get electrical supervisour certificate in gujarat

0 Answers  






What is the application of Nitrogen Injection system in Transformer Protection?

1 Answers   HPL,


Dear all: Recently we got a question about Interface between PMS and SAP-PM.once we got a update message from PMS.we should set the deletional flag for functional location in SAP system.Is there any FM or BAPI to use?There are only functional location create and change provided by SAP. Best regards!

0 Answers  


what happened if power factor is "1"

9 Answers   Reliance,


pls send me some question and answer for rrb railway interviw related 2010

2 Answers   CEAT, RRB,


types of motors suitable for escalators with reason

2 Answers  


which IS or IEC is used for earthing,breakdown voltage of transformer oil, hv/pd testing and all type of electrical testing

0 Answers  


why high current produce in case of transformer when turns are internally gets shorted.

3 Answers   TCS,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)