Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

what"s the difference between fe 415 grade steel and fe 500
grade steel? and which one is mostly used for residential
and apartment constructions?

Answer Posted / mustafa mohammed layeak

Fe 415 yield strength is less than Fe 500. But Fe 415 is more ductile than Fe 500. Fe 415 means its yieild strength is 415 N/sqmm (415 MPa). Fe 415 is mostly used in residential buildings.

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to avoid fly ash seed ball formations in the concrete mixer while mixing of raw materials for fly ash block manufacturing?

1892


Please design 12.5m long dubbly beam

1887


What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?

2849


i have four storeyed rcc building.basement of the building is around 34 years old.it does not have pillar support.it is having lintel steel support at every 7 feet of construction. how long this building will lost long . can any body help me in this regard

2343


I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.

6066


How much form and scaffolding per cubic meter volume of concrete class ''A'', ''B'', and ''C''

2161


What is the standard specification of MOR and Water Absorption of Homogenous Ceramic Floor Tiles?

2222


yasser arfatcompleted his degree in civil from which university

2253


what"s the sort of beams?

2307


What does civil engineering mean?

1075


What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.

2107


How many square meter can mason layout chb per hour

2253


What is the average density of soil?

1245


How to calculate or what is the process of calculation for making 1Metre squre area by AAC Blok which quantity of Cement, Sand & Chips are to be required?

1870


i am laying a base of dimensions 6.5feet by 7feet by 1.25 feet depth how many bags of 25kg cement and how many bags of 25kg sand will i need

2477