How Can Calculate Plastering Quantities For 260.04 square meter by using CM 1:4 with 25mm Thick ?
Answer Posted / rrbharathreddy94@gmail.com
Plastering with CM = 1:4
Thickness = 25 mm
Area to be plastered = 260.40 square meter
Thickness of moter layer =25mm=0.025M
volume of moter required =260.40X0.025=6.51 Cum
Add 15 percent of allowences for undualation of surface & wastage = 6.51/100X15=0.976Cum
=6.51+0.976= 7.486 Cum ( total Volume of moter required)
Sand required for 7.486 Cum of CM 1:4= 7.486 Cum
Cement required for 7.486 Cum of CM 1:4= 7.486/4=1.871Cum
Wt of Cement Required =1.871X1440=2694.96 Kg = 2695 Kg (say).
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
if i used salt as a add mixture in concrete, then what will happen and what are the naturally available add mixtures.
how many men days of loburs and masons are requirete for 1 cum,pcc (1:2:4),Pcc(1:3:6) and Pcc(1:4:8) thanking you
do you think we shall remove un wanted soil for foundation excavation even if the thickness of the soil strata is more than 8m ?
what is the types of surveying?which type of survey carrying for type of work?
strength vs shape factor
how to calculate the concrete mix m30 by volume
Sir how to find cutting length for footing steel bars in the shape of "u"
How u can calculate the Octagon ring distance from center of raft in 275 mtr chimney slipform errection? cantact no:0993455097
types of laps in column
wat would be the probable interview questions and GD topics for IOCL exam?
For 1 bag cement how i will calculate sand and metal aggregate;Here the mix proportion is 1:2.49:2.38
Draw a neat sketch showing the 'throat' of a welding in a plate girder ?
can we make bricks using m10 grade cement concrete and what would be the ratio of raw materials used and price per brick ?
what is difference between GTS bench mark and temporary bench mark
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?