How Can Calculate Plastering Quantities For 260.04 square meter by using CM 1:4 with 25mm Thick ?
Answer Posted / rrbharathreddy94@gmail.com
Plastering with CM = 1:4
Thickness = 25 mm
Area to be plastered = 260.40 square meter
Thickness of moter layer =25mm=0.025M
volume of moter required =260.40X0.025=6.51 Cum
Add 15 percent of allowences for undualation of surface & wastage = 6.51/100X15=0.976Cum
=6.51+0.976= 7.486 Cum ( total Volume of moter required)
Sand required for 7.486 Cum of CM 1:4= 7.486 Cum
Cement required for 7.486 Cum of CM 1:4= 7.486/4=1.871Cum
Wt of Cement Required =1.871X1440=2694.96 Kg = 2695 Kg (say).
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What is the use of mirror command?
how to find the cement bags and sand requirements for the one square meter of internal,external,ceiling plastering by using the various ratios like 1:3,1:4,1:5,1:6
How much material is required for constructing a 2 Lane 2Km rigid pavement road
Curvature ki quantity kaise nikalte hai pls give me ans... curvature canal ka hai
Reinforced concrete: suppose you are doing rough estimate for purchase of rebar for reinforced concrete slab for single stores residential building. You know total concrete volume will be 100 m3. How many tons rebar 6, 10 and 12mm will you require for the project?
What is an ice dam sock?
how to calculate cut length of re-bar in a circle . because we not place same length of re-bar in whole circle maximum in center and minimum at corner so how to calculate middle bars???
The 4 main factors to start a construction project are––
dialation means
Why should pumping be not used in case of concreting works?
What is thumb rule in quality and quantity estimation of a Residential building??
How many days should curing of plastering, brick work and concrete
How to cal. The weight of hollow pipe?
what is pouring and explain
How do you measure water flowing through 300mm diameter pipes?