How Can Calculate Plastering Quantities For 260.04 square meter by using CM 1:4 with 25mm Thick ?

2 Civil Engineering 2599




Answers / { bharath kumar reddy . ramiredd }

Question { 2599 }

How Can Calculate Plastering Quantities For 260.04 square meter by using CM 1:4 with 25mm Thick ?


Answer

Plastering with CM = 1:4
Thickness = 25 mm
Area to be plastered = 260.40 square meter
Thickness of moter layer =25mm=0.025M
volume of moter required =260.40X0.025=6.51 Cum
Add 15 percent of allowences for undualation of surface & wastage = 6.51/100X15=0.976Cum
=6.51+0.976= 7.486 Cum ( total Volume of moter required)
Sand required for 7.486 Cum of CM 1:4= 7.486 Cum
Cement required for 7.486 Cum of CM 1:4= 7.486/4=1.871Cum
Wt of Cement Required =1.871X1440=2694.96 Kg = 2695 Kg (say).