How to calculate the shuttering materials i.e MS sheet,Props,Acrow Spans,2'x3' Runner,4'x3' Runner & beam plywood bottom, sides in thumb rules in slab area
Answer Posted / syed abdul kadhir
For example span will be 10' * 10'
Sheetsize 3'*2'
X axis 3*3=9'+1 feet plank throughout 10'=9+1=10'
Y axis 2*5=10'
Total number of sheet will be 15 and 1feet plank (10')
Prob will be provide in each 2ft
No of probs is 15.
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
what are the grades of concrete?where and or what purpose a particular grade is used in a particular structure?
how much need sand and cement for 1 cft roof construction?
Minimum concrete cover in slabs, columns, beams, foundation and other st?
How you read 5x3x1 #4 @ 20" 0/C in steel structure?
Why are the bolts that hold steel rails together in oval holes?
What are the joints wants to made in masonry where door opening, arches like etc..
What do we mean by partial moment release ??
When column of building is abutting the boundary line,then suitable footing advised is
what happening if we casting HV shunt reactor foundation pad at 50cm height different time (One day difference)
Explain what is progress payment?
How do you compute the volume of airflow?
Define What is rigging?
what is cement wastage percentage in NHAI ROAD WORKS
what are the duties of Site Engineer in work site?
For what purpose bedding is used under storm water drains, explain?