how do we calculate quantity of cement , sand and
aggregates in 1 m3 of M30 grade concrete ?
Answer Posted / sunil kumar yadav
Taken the ratio-1:1.5:3
cement-1
sand-1.5
metal-3
so ratio will be for mixing-1+1.5+3=5.5
Totals ingredients forusing to=1.54/5.5=o.28
cement solution=0.28 cum
send=0.28×1.5=0.42 cum
(1.5 is a maximum proportion)
metal=0.28×3=0.84 cum
(3 is a maximum proporties)
1 cum cement concrete ratio is 1:1.5:3
cement=0.28 cum
Sand=0.42 cum
metal=0.84 cum
so cemenbbage will be =50/1440=0.0347
(1440=unit wait of cement & 50=wait of 1bage cement)
so cement bags will be=0.28/0.034=8.24 bage.
| Is This Answer Correct ? | 0 Yes | 2 No |
Post New Answer View All Answers
who to find building iron rod strenth
What is the worlds largest concrete dam?
how to calculate labour strength for work for RCC,brickwork,blockwork,in &out plaster,flooring,dado,door frame & shutter,painting etc for constructing highrise building?
hi guys what happens if you are absent for a supplymentry exam?
Can anybody explain with the help of sketeches that what are 2legged , four legged & 6legged stirrups and how to calculate cut length of diamond ring(stirrups)?
Hi how r u ? hope you are fine there . Please can u tell me tha Design life of Buildings as Per ACI CODE 318-99. It will be a pleasure for me .Thanks in advance
length where bent up is made in slab of bridge from one end
Used Cement & Sand in 1 Square Meter or 1 Square Feet For Brick Work 0.115mm ? (1:4) (1:6)
I am a civil engineer . I am also selected for sbi clerk interview which is to be held on 4th May2010 is there anybody resembling the same? what question can be asked and what should be the probable answers?
Could you please give me an answer to the mixing proportion of concrete M1 grade (sterngth of 1 MPa)?
a sewer which receives the discharge of no. of house sewer is called house sewer lateral sewer intrcepting sewer sub-main sewer
what is civil all interview questions
What are the applications of cad?
why we use 19x9x9and 20x10x10 but not other
what is difference between NP2 NP3 NP4 CONCRETE HUME PIPES USED AT SITE