how do we calculate quantity of cement , sand and
aggregates in 1 m3 of M30 grade concrete ?
Answer Posted / prakash pandiyan
for designing 1m3 concrete of M25 mix the ratio is 1:1:2
for calculating cement,sand and course aggregate ,
for 1m3 add 50% for shrinkage and wastage so 1.5m3
1.5m3/(1+1+2)=.375
density of cement =1440kg/m3=says 1440/50=28.8bags
cement required for this mix=.375*28.8=10.8bags
sand=.375*1=.375m3
course aggregate=.375*2=.75m3
FINALLY WE SAY 10.8 BAGS/M3
| Is This Answer Correct ? | 7 Yes | 3 No |
Post New Answer View All Answers
Please tell me the quantity of cement, sand, flyash, foaming agent required for 1 cubic meter of cellular lightweight concrete blocks. also , is there any admixtures required for the CLC blocks production.
How musch steel i.e. angles, channels,and square pipes are required per square feet for a steel roof of residential two storied building?
what are the code used for residental building?
While doing civil foundation of machinery. How will you process for it? & We also fixing plates at top surface of foundation, then what is the procedure?
what isload waring calculation
Is there any course for billing available in Mumbai? If yes then please mail me the details..
How to arrive dry volume of concrete (1.52 to 1.57) ?
Give me an example of a time when something you tried to accomplish and failed.
what is the most suitable foundation when construct a bird watching tower in a marshy land
What is the number of IS code of practice to be followed for hydraulic design of sewerage pipe line?
what is smart building materials?
What should be the standard roof height like to be?
What type of tensile strength is handling by crank in beam? Thanks.
What is dead load impact load live load
B.M DIAGRAMS & S.F DIAGRAMS OF CONTINOUS BEAMS