how do we calculate quantity of cement , sand and
aggregates in 1 m3 of M30 grade concrete ?
Answer Posted / k.nabadwip sharma
Calculation for Cement:-
100 cft of conc in loose 144 to 154 cft required,average of
144 and 154 is 149 cft say 150 cft.
M25 = 1:1:2=4
150cft/4=37.5cft
37.5cft/1.2=31.25bags [1 bags of cement is 1.2cft]
=31.25/2.83=11bags [1 cft = 0.0283cum x 100 cft=2.83cum]
per cum cement required=11bags
Calculation for Sand:-
11bags x 1.2 cft = 13.2 cft = 13.2 x 0.0283=0.374 cum
Per cum sand required = 0.374cum
Calculation for Aggregate:
=0.374 x 2 = 0.747 cum
per cum Aggregate required = 0.747 cum
| Is This Answer Correct ? | 1 Yes | 5 No |
Post New Answer View All Answers
Material calculation of cm 1:6 for 1sqm
what are the values of compressieve strenght?
how to calculate testing date
Coverage of 25mm.thick ratio of 1:4 cement mortar?
contractor receive 100 MT steel.after compliting the work the contractor refund 90 MT steel.How reconsilation of steel done?
Explain what is alternate bid?
Which code specifies the specification ofthe construction joints to be provided in the raft slab of a basement which is 6 m deep.what should bethe detail of such a joint?
how much cement and sand required for 1cum rr masonry
How do you compute the volume of airflow?
How can i do RCC rate analysis?
What is the Systematic Responsibility Site Engineer? Who are the above and under co-oridinating ? What is office & Site co-ordination of Site Engineer?
What do you mean by the word 'shear'?
What is .Dwg?
all technical question
What are the main reasons for conducting pull-out tests for soil nails?