How many number of bricks required for 1 cum & how much mortar
quantity require for 1 cum
Answer Posted / m.k. dharmaraja
The brick size
1. 21x10x7.5= 380 to 400 Nos Mortar is 1.1 bags Cement(1:5)
2. 20x9x4.5 = 400 to 430 Nos Mortar is 1.25 bags Cement(1:5)
3. 19x8.5x7 = 450 to 480 Nos Mortar is 1.45 bags Cement(1:5)
This data is as per site details
Add the wastage in the quantity for 10percentage for all
above.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
I need Bhel engineertrainy test papers in civil engineering please send to email id - hisandy66@gmail.com
What is the diameter of the 3"inch nails?
I am doing a engineering contract with GOI. I have purchased certain material from outside Maharashtra and paid CST on that material @ 5.25%. Please intimate whether I will be liable for VAT or VAT on works contract or not.
Rate analysis of Vitrified tile in cement mortor 1:3
difference between trapezoidal and pedestal footing and how the load acts on that
What is the largest concrete dam in the world?
how to calculate the weight of concrete
Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.
five benefits of using standard terminology in the measurement process
how to check and keep control on the wastage of material at site
why we provide bent up reinforcement bars at l/4 ? if it is because of diagonal shear , how does it acts ?
Form where IS456 is adopted in 1978?
how much shouid be the rate for ready mix concrete per cubic meter
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
Hi my name is Binyam and I'm a 7th grader at Mayfield Woods Middle school. I decided to research civil engineering as my career and i need to know a few thing about your profession. What is your daily routine? What are some advantages and things you like about your job? What are some disadvantages What is the hardest thing you have done? What education have you gone through to become a civil engineer? How long is your work day? What is your work environment like? What is your salary? What made you want to become an engineer? What tools do you you use? Thank you for answering my questions