how do we calculate quantity of cement , sand and
aggregates in 1 m3 of M30 grade concrete ?
Answer Posted / manish singh
M-30 Grade Concrete=
Ratio-1:1.5:3
1mq concrete
Cement => 1*1/5.5=.182 (5.5=Mixing)
=> .182*1.5=.273 (1.5 *dry moisture)
=> .273*30 = 8.19 (8 bags /409.5kg)
Send => 1*1.5/5.5 =.273
=> .273*1.5 =.410 mq
Aggregate => 1*3/5.5 =.545
=> .545*1.5 =.818 mq
| Is This Answer Correct ? | 5 Yes | 7 No |
Post New Answer View All Answers
How much for the BRC lapping in full yield and half yield < and which table to get it ?
Who designed the city of washington dc?
What are the reasons for geotechnical site investigations in uganda?
What is the use of extend command?
What glue is least sticky?
i have applied 40mm spacer in the concrete for tie beam. is it correct? kindly give me if there any code available
cud any one send me tech quest paper(civil engg) at tarizus@yahoo.com
How to calculate or what is the process of calculation for making 1Metre squre area by AAC Blok which quantity of Cement, Sand & Chips are to be required?
Can anyone suggest how to determine scheduling of reinforcement of floor beams from Staad model,other than clicking each beam respectively 7 noting down the values ?
What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)
what is parametre for M25 after 7 days strength
How to decide/consider the grade of bitumen for dbm.
Rate analysis for construction of a solid block masonary of size 400x200x200 in C.M.1:5 in superstructure .Compressive strength 5.00 N/Sq.mm Confirming to IS: 12894:1990, with necessary scaffolding, raking of joints and pointing the same. I require rate per Cum.
1m square 20mm plastering how much of water need curing work
What is rolling stock