Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how do we calculate quantity of cement , sand and
aggregates in 1 m3 of M30 grade concrete ?

Answer Posted / enayatullah

Take the retio 1:1.5:3
Cement = 1
Sand = 1.5
Aggregates = 3
The volume of none mixed material is 1.52 m3 for one cu.m
mexid concret becouse the the aggregate sand and cement
have porosity that will fill with some of sand and
cement,so 1.52/(1+1.5+3)=1.52/5.5=0.276
Cement=0.276*1=0.276 cu.m = 0.276/0.036*50 bag = 383kg
0.036 is one bag volume
Sand = 0.276*1.5 = 0.414 cu.m
Aggregate = 0.276*3 = 0.828 cu.m
0.276+0.414+0.828=1.518 near to 1.52

Is This Answer Correct ?    45 Yes 27 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to construct a water sump in a rocky soil?

2217


How do you change a dimension value in solidsworks?

1240


How can you produce desired alloys and discuss their applications in daily life.

1231


In the design of bridge arguments what considerations should be made to select the orientation of the wing walls?

1090


How is the leaning tower of pisa supported?

1074


How many square meter can mason layout chb per hour

2278


What Reinforcements Are Used In The Process Of Prestressing?

1342


step by step procedure to find out the percentage of steel in coloum,beam,slab,footing in detailed

2448


how to control PQI (Project Quality Index)

10892


How to do rate analysis for concrete work including shuttering work?

2050


Describe the role of independent Quantity surveyor?

2889


a rectangle grill of length 72 inch x 20 inch width.how to calculate bar spacing ,bar consist 8 mm thickness and spacing of bar is 2 inch.. calculate no of bar with formula

1686


What are the advantages of cad software’s?

1103


what is the difference between prime coat and tack coat in road construction

5046


Explain what is the release of lien?

1236