how do we calculate quantity of cement , sand and
aggregates in 1 m3 of M30 grade concrete ?
Answer Posted / tukuna das
M30 means , proportion 1:1:2 , so that
Total Volume = 1m3
we take 52% extra for dry volume , miss handling etc then ,
total volume = 1* 1.52 = 1.52 m3
Quantity of cement required = 1.52/(1+1+2)=0.38/0.035= 10.857bags = 11 bags
Quantity of sand required = 0.38*1=0.38m3
Quantity of aggregate required = 0.38*2 = 0.76m3
| Is This Answer Correct ? | 12 Yes | 12 No |
Post New Answer View All Answers
what is mc arther pile?
what is the formula for Mass of cement grout (Dg)=???
How to Know that veriation acceptable in CPWD Work Of 1:6 Cement Mortor Received Lab test report.
How to check slab shuttering level.? Or check list for slab ?
I want to change job.If You have any vacancy please contact me in this mail id-parthamitra086@gmail.com.Myself partha mitra.Diploma in civil engineer with 4+ yrs. exp.Now in kolkata.If you confirm me then I will send my detail resume to you.Also send your mail id to me.My mail id is-parthamitra086@gmail.com.I will be very much thankful to you.
why we provide bent up reinforcement bars at l/4 ? if it is because of diagonal shear , how does it acts ?
what pressure the NP2 class RCC pipe can sustain?
which formula used for calculate the area of segmental arch?
explain the rale of the government in the construction industry
length where bent up is made in slab of bridge from one end
Need help in designing a degasser tower for 2m3/hr DM plant, also send me the formulae used
what is the painting co efficient of slope roof tiles?
HDPE pipe standard bends using for TSE irrigation? is it possible to use 30 degree?
How to arrive d*d/162 , for finding the kg per meter , wt of steel
pls give me ans to ACT formula cube testing porpuse