I want formula to calculate cable size as per load given in
kw & amp.I searched many sites but didn't right answer.Plz
reply me asap.
Answer Posted / tushar jana
I dont understand why people are complicating the issue....
the answer is very simple.
Consider Cable selection for the 3ph motor of 1kW
Formula>> P= root(3) x V x I x Cos(Phi) x Eff
p= power... Say 1kW
V= voltage (415Volt)
I= Unknown
Cos(phi)= 0.85.. say
Eff= Efficiency..= 0.85... say
Now,calculating this, we get>> I= 1.9Amp.. say approx 2A
Now derate this current (bcoz, cable will be laid in duct
or undergroung,etc) consider derating factor as 0.7 (say)
Then current is 2A/0.7=2.85A... say 3A..
now see the cable catlogue of any company.. say polycab..
See which size of cable can carry 3A current and use it...
thats it..
Approx.. for 1kW motor, 3Cx 2.5 Sq.mm cable is sufficient
upto 275m length.
NOTE: This is rough method of calculation. If cable length
is more or motor size is more... then voltage drop
calculation is also to be done.
Contact- 9665065050
| Is This Answer Correct ? | 19 Yes | 4 No |
Post New Answer View All Answers
What is the difference between relays and contactor construction wise?
Dear friends I want to design busbar for1600 kva transformer(i.e2100 amps) what are all the factors to be considered before selectinga busbar what are all the standard sizes of busbars what is the formula for finding current of copper and aluminium busbar
Determine a suitable number of slors and conductors per slot for the starter 1 winding of a 3 phase, 3300 V. SO Hz 300 rpm alternator. The diameter is 2.3 m
specific difference of ICT&Auto Transformer
What is the one main difference between ups & inverter ? And electrical engineering & electronics engineering ?
wheather the size of windings in motor and generator are the same
What should be current in the Primary and secondary side of 1000KVA (11KV Supply)Transformer.?
How to do stting of vl250 siemens MCCB
how to calculate earth fault relay current and CBCT ratio
I completed iti in2004 I was worked in A grade contractor can I get c licence
What does Bode plot tell you?
Compare salient pole and cylindrical rotor machines.
how to calculate cooling requirement of datacentre from electrical load?
What is a feedback in control system?
how much cable size required for 70 kilowatt load.