Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to calculate sand,cement for 1:5ratio brick masonary

Answer Posted / sandy

suppose u have to do 1 cum b/w

now 1:5 c.m. and using fine sand (jamuna sand)

1+5=6

1/6 x 1440 x .292 = 70.07 kg
5/6 x 1525 x .292 = 371.08 kg

cement density 1440/cum
fine sand density 1525/cum

total volume for 1 cum b/w .292cum


so simple

Is This Answer Correct ?    20 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

is it fair to recruit another prestressing agency once earlier agency has provided guide cone for post stressing the Concrete -I girders? It is observed that the bearing plate of another agency is not matching with the earlier one resulting in protruded strands after stressing from the face of girder. Kindly advice.

1913


Which is the direction for positive angle?

1216


What is need for setting limits?

1091


When was the first motorway built in england?

1020


where will be the reinforcement of slab placed when there is an inverted beam and the bottom of the beam and slab are at same level ?

1282


Why M15 is replaced by M20 when ammendment are made in IS456 in 2000?

1637


What are the causes of building collapse?

1111


What are the composition of a landfill?

1171


what is cross hair cursor?

1054


I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.

6031


what is castigliano theaorem

2222


What is meant by cad?

994


What is c.g.i sheet which used for roof??

1870


Explain why concrete barriers have curved surface profiles?

1205


all technical question

2205