Answer Posted / tushar patel
AS per IS:456-2000,Concrete grade above M25 has to be
designed mix.for such higher grade W/C ratio,quality of
aggregates,admixtures are equaliy important parameters.So
M30 can never be designed in volumetric batching if
consistent quality control & strength is desired.
| Is This Answer Correct ? | 29 Yes | 4 No |
Post New Answer View All Answers
how much repeitation for conventional and maivan formwork?
how do i remedy a foundatiom that the column bases was cast and aftet 28days crushing the conprehensive strength of the concrete fall below the specification 25N/mm2
how pumping of concrete effects the quantity of material used in it?
what is c4x light weight cement blocks
difference between trapezoidal and pedestal footing and how the load acts on that
what are the Task work of different labour.?
What is the minimum size of the particles of silt soil?
give me the rate analysis for Bituminous Macadam and SDBC
what is the painting co efficient of slope roof tiles?
(Project Management Topic) What are the important criteria in the successful realization of the project?
Define graphics window?
What materials were used to build the golden gate bridge?
what is the coefficient for running feet to cft coversion both area and price
What are the applications of cad?
Define current ucs?