how do we calculate quantity of cement , sand and
aggregates in 1 m3 of M30 grade concrete ?
Answer Posted / subilash .s(civil engineer)
for designing 1m3 concrete of M25 mix the ratio is 1:1:2
for calculating cement,sand and course aggregate ,
cement= 1/(1+1+2)=.25
density of cement =1440kg/m3
cement required for this mix=1440*.25=360kg=6bags+10kg
sand=1/4=.25m3
course aggregate=1-.5=.5m3
this methode of designing is known as volume batching ,this
methode will be ues to design mixes upto m25.
| Is This Answer Correct ? | 86 Yes | 69 No |
Post New Answer View All Answers
What is the per cu. mt. price of ready mix in Gujarat region.?
Why Is Propping Required For Long Structures Once The Form Work Is Removed?
What are the alternate material for steel, Sand and aggregate
how much concrete solid/hollow block are manufacture per 50 kg cement bag in differnent sizes like 400x200x200mm, 400x200x150mm, 400x200x100mm. And need proper ratio as per sale quantity. pls send my mail mathi7599@gmail.com searching last two years not yet get pls find and enclosed pls. need practical analysis.
20mm thick sand face plaster on walls consisting of 12 mm the backing coat of c.m.(1:3)and 8mm thick finished coat of c.m.(1:1)including scaffolding, watering, finishing etc complete please calculator with methyl et et r u
by which materials we can prepare circular shuttering with tentative cost of material(rate analysis)
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting?
Elaborate advantages & disadvantages of using crusher dust instead of sand in rcc work.
What is the meaning of soil reinforcement?
What is the cemnent ratio
If we buy crush sand for 3200/ Brass and cement for Rs350 /Bag and flyash 1200 / tonne....and my production is 230 Bricks per bag than how much cost is required for 1 flyash brick?
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh
I have an span length 16 ft c/c
What is packing Factor ?
what is the metal ratio in granular subbase coarse for one cum ? And please explain the morth table ...what is the difference between grading 1 , 2, 3 what it means..plz explain