how do we calculate quantity of cement , sand and
aggregates in 1 m3 of M30 grade concrete ?

Answer Posted / subilash .s(civil engineer)

for designing 1m3 concrete of M25 mix the ratio is 1:1:2
for calculating cement,sand and course aggregate ,
cement= 1/(1+1+2)=.25
density of cement =1440kg/m3
cement required for this mix=1440*.25=360kg=6bags+10kg
sand=1/4=.25m3
course aggregate=1-.5=.5m3
this methode of designing is known as volume batching ,this
methode will be ues to design mixes upto m25.

Is This Answer Correct ?    86 Yes 69 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

about higyway engineering

3572


Civil engineering related

1524


mean of NH4 pipe

2119


During reclamation how can the occurrence of mud waves can be rectified?

831


Explain what is zoning permit?

776






How much cements bag (or in KG) required for 1 Sq. M concrete, for M-30 grad concrete as per CPWD and where is thr proof on site

1227


what is E VALUE FOR WOOD

1539


what is your role of in previous company as a construction manager

1574


Hollow block masonry in cement mortar 1:4, 40×20×20cms in superstructure take 10sqm.I want calculation of brick sand

1266


When column of building is abutting the boundary line,then suitable footing advised is

1963


What is a hatch patterns?

680


in a corner footing of a building, column lies in one corner. in this condition i want to know if the reactive pressure of soil will be uniformly distributed throughout the footing or will be uniformly varying as in the case of eccentrical loading.

1731


How should we design a brick column and footing?(note: no reiforcement to be provided) Can you tell me any reference book where i could possibly find this design? Plz help urgently

2068


TELL ME THE EQUATION FOR OGEE SPILLWAY

2179


which formula used for calculate the area of segmental arch?

2364