i am working in thermal power plant .
if temperature transmitter is not showing reading in dcs
then how can we rectify the problem?
Answer Posted / g kiran kumar
1. Check the wiring at all terminal blocks at field, at
control panel and at PLC for any loose connection.
2. Check the Transmitter supply.
3. Measure the output from Transmitter.
4. Check cable continuity.
5. Finally check the configuration of TAG in the DCS (may
be someone deleated accidently).
| Is This Answer Correct ? | 6 Yes | 0 No |
Post New Answer View All Answers
full process of gas turbin?
hi my name is rakesh patel i just complited my be in instrumentation & control now i am going to working as a validation engineer in a poject department so what is a scope in a future as a validation engginer ? what line is good for me can any bady give me complete solution please? your regard rakesh patel
hello friends, can you please send me the model paper or question paper to be prepared for hpcl examinations????????? You can mail me at rahim_here@yahoo.com waiting for your reply........... help me .. plz.....
1)How many tpes of vibration probe and how many tpyes of vibration. 2)how we can calibrate a vibration probe with tk3 3)what is RMS value in vibration measuring application and how we calculate it.
HOW TO CHOOSE FREAQUENCY IN FMCW TYPE RADAR INSTRUMENTS. DESIGN BASIS OR DESIGN CALCULATONS ?
how to convert cubic metre per hour to newton cubic metre per hour
How RAL(Rotary air lock)works in cement industry?
how many types of viberation transmitter and how to calibrate and where use of vibration transmitter
What is compensation for flow ? Why we use compensation ? What are the factors of different compensation ? We not use then what problems may happen ?
what is the process to make control schematic ?
What is heating effect?
what is IEC code in cables & how to selecting cables?
What is Erosion in a control valve?
What is first echo & echo window in radar type level transmitter?
Can combine control system for Emergency control system (ESD)and Fire & Gas System ( F & G) is possble to built and offer to client? Can such system is as per Norms in India?