Answer Posted / jai.vignesh
As per Indian Standards:
1. Vertical form work to Beams = 16 to 24 hours
2. Props to beams Spaning up to 6.00m = 14days
3. Props to beams Spaning up to 6.00m = 21days
4. Props to be refixed immediately after
removal of form work = 7days
| Is This Answer Correct ? | 11 Yes | 2 No |
Post New Answer View All Answers
WHAT DLC DESIGN IN CONSTRUCTION
How to calculate the crank rod in slab
construction workers how much time take one work or qty
Define What are the reasons for geotechnical site investigations in Uganda?
does a b.tech civil engineer fresher supposed to know how to design rcc structure?
How to find CN by using arcgis 9.3?
what is the permanent solution applied for restoration of leaning tower of pisa?
Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required
What is Curtailing of R/F
What is the mix propotion of M10,M15,M20,M25,M30,M40,M50.M60 cement content,aggrigate,sand and water ratio.
What is the difference between undo & redo?
i want to ecil (Electronics Corporation of India Limited Hyderabad) previous civil engineering question papers immediately please.............
What is the substitute of Mastic Asphalt?
resins are not soluble in water soluble in spirit used in varnish left behind on evoporation of oil
What are the phases inspections are done by local authority while construction?