how do we calculate quantity of cement , sand and
aggregates in 1 m3 of M30 grade concrete ?
Answer Posted / randeepchaudhary
if we consider concrete grade M20(1:2:3)
1+2+3=6
wet volume 1.58cum
cement = 1/6x1.58=0.26cum
volume of one bag of cement = 0.033cum
total quantity of cement bag one CUM concrete =0.26/.033=7.87bags
7.87x50 kg=393kg
| Is This Answer Correct ? | 48 Yes | 75 No |
Post New Answer View All Answers
What is the largest concrete dam in the world?
115mm thickness brick work how to required mortar
I Want To Know Quantity of Cement Conc. & Sand in Column of 9"x9"x10'
For Wet Mix Mecadam design what is Optimum moisture content
Need help in designing a degasser tower for 2m3/hr DM plant, also send me the formulae used
2nd and 4rt angle elevation used in which country ?
how to prepare site mix design
Why Is Propping Required For Long Structures Once The Form Work Is Removed?
how much quantity of cement,sand and water required for 1 sq feet flooring work .
At what point does a circle start losing area when being flattened?
Process of pcc in wateredug
How do we calculate absolute pressure?
from where ican get sample papers for CET-delhi 2012
Design a reinforced concrete combined footing (rectangular) for two columns located 3.60 metres apart. The overall sizes of the columns are 40cm x 40cm and 69cm x 60cm and the loads on them are 1000 kn and 1500 kn respectively. The space available for the width of the footing is restricted to 180cm. The S.B.C. of the soil is 280 kn/mm2 use M15 concrete.
what is the max. area can we apply the plate load test ?