Answer Posted / ashalatha y
Proportion: 1:1:2
Quantity of Cement= 1440*0.92*2/4
=662.4 Kgs
=13.248 Bags
=13.5 or 14 Bags can be taken
| Is This Answer Correct ? | 39 Yes | 70 No |
Post New Answer View All Answers
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh
1)Why we can use half brick in 4inch wall and 2)why not in 9+inch brick wall
How to calculate construction cost of residential building in mumbai
What are the phases inspections are done by local authority while construction?
Draw a neat sketch showing the 'throat' of a welding in a plate girder ?
Permissible wastage of cement as per IS code ? In which IS code I get it?
how to take the quantity of block work and plastering 1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate
in 100 cft = 1350 bricks in 100 cft = ? bloks
What is the general specifications of a bituminous pavement road?
What is the ideal size of the living room ranges from small to large size?
can you give me the details of rate analysis of steel and concrete?
What is difference between combin footing & rapt footing
what is the quantity of block work required to construct a compound wall of 6" thick,and 212 lenght
can any one tell me in detail footing estimation .. i am new here in dubai so facing lots of problem...
Which condition will prevail for the design of a swimming pool ? When the pool is empty or when it is filled ?