how do we calculate quantity of cement , sand and
aggregates in 1 m3 of M30 grade concrete ?
Answer Posted / sjtbehera
In the case M30 concrete we calculating by design mix.but
incase of norminal mix we can use 1:1:2.
calculating cement, sand and concrete.
toal ratio=1+1+2=4
cement = 15.4/4=3.85cum=11bags
sand=3.85*1=3.85 cum
chips=3.85*2=7.7 cum
Notes: why we divided 15.4
but it is difficult to acess exactly the amount of each
material recquired to produce 1cum.of wet concrete when
deposite in place.
to find out volumes of cement sand & coarse aggregate
divided a numerical no. 15.4 variable up to 15.7 according
to proportioning and water cement ratio by the summation of
the proporation of the ingrediants used and then multiply
the result thus obtained their respective srength of
proportion.
| Is This Answer Correct ? | 156 Yes | 216 No |
Post New Answer View All Answers
sir how can we find the cement and sand required for making 4" drop
How do we determine the specific gravity of a cement?
16 questions out of 55 were from the book GUPTA N GUPTA OBJECTIVE of civil engineering. Total ques were 4 ques from hydraullics, 7 from BMC, 4 FROM SOM, 4 from soil mechanics, 6 from transportation, 5 from engineering drawing.
what is the use if we fixed butterfly ties in column and masonry work joint?....where we have to fix(distance)..
what s the standrd size of pvc fittings ,like elbow, bend,tee etc ? please explain with figure ?
How much 1 cum of M15, M20 & M25 concrete weigh?
Why are steel plates inserted inside bearings in elastomeric bearings?
Does VDF add strength to the flooring apart from preventing water ingress?
How to calculate or what is the process of calculation for making 1Metre squre area by AAC Blok which quantity of Cement, Sand & Chips are to be required?
How is make concrete cube?
What is the density of 1:1.5 (Cement:sand) ratio in plaster? And Conversion in 12.5 mm thickness per square meter? Howmany Kg of Cement square meter in ratio of 1:1.5?
57. Calculate the volume of a truck loaded with stone chips whose data are as follows– 5 Top Length - 13-9, 13-10, 13-09 Bottom Length - 13-11, 13-10.5, 13-10 Top width - 8-7.5, 8-8, 8-7 Bottom width - 8-7, 8-8, 8-7.5 Depth - 2-0, 1-11.5, 1-10, 1-11, 1 -10.5, 1-11.75, 1-11
How cracks in concrete can be avoided?
how to take concrete quantity for precast segment for viaduct project?
how much of quantity of material required for execution of one cubic meter of random rubble masonry in 1:3 cement mortar