Answer / rohit dhingra
for this we need the given concrete grade as for m20.
calculate volume in cum = 1x0.2 = 0.2 cum
for m20 multiply with 8.064 for cement = 1.61 cement bags
sand = 0.42x0.2 = 0.084 cum
aggregate = 0.84x0.2 = 0.168 cum
| Is This Answer Correct ? | 2 Yes | 6 No |
what is the main disadvantage of concrete at environmental point of view.
What out turn civil works
what is meant by concrete joints?
sir i have 2700sq.ft area.i wish to make a coomercial space including this area.sir what could be the estimated cost of 3 story bulding in varanasi.
I have to conduct load test on greting cover, pressure gauge is in kg cm2, how to caluculate load on this greting cover.
concrete strenght is increased if using sisal fibre in concrete?
BASIC DIFFRANCE BETWEEN LIMIT STATE METHOD AND WORKING STRESS METHOD?
what is the different between np2& np3 rcc hume pipe
How much block, cement,sand,is required for 1 sqmt of 200*200*400 block work
please differentiate duties and responsible for civil site engineer , Quantity suryevor ,Quality control engineer and Planning engineer
What is the name of this multiplication factors ?
0 Answers Engineers India Limited, L&T,
age of tree determine by redius of its items circumference of its stem no. of branches no. of annual rings
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)