What is NPV? What is IRR? What is the difference between NPV
and IRR method? Which and why among NPV and IRR do you think
is more appropriate technique in capital budgeting?
Answers were Sorted based on User's Feedback
Answer / manoj
NPV is the Net Present Value . It is the summation of
present values of future cash flows less the present value
of cash outflow. This method takes into accoutn the time
value of money. Generally present value of cash outflow is
determined by multiplying with the discounting factor which
is the cost of capital of the company.
IRR is the Internal rate of return . It is the rate at
which the PV of Inflow is equal to the PV of outflow.
If IRR is positive then we can go with the project else
ditch it.
For capital budgeting decisions a mix of techniques is
used. No single method is accurate enough.
| Is This Answer Correct ? | 74 Yes | 16 No |
Answer / rudradeva
Key differences between the most popular methods, the NPV
(Net Present Value) Method and IRR (Internal Rate of Return)
Method, include:
• NPV is calculated in terms of currency while IRR is
expressed in terms of the percentage return a firm expects
the capital project to return;
• Academic evidence suggests that the NPV Method is
preferred over other methods since it calculates additional
wealth and the IRR Method does not;
• The IRR Method cannot be used to evaluate projects where
there are changing cash flows (e.g., an initial outflow
followed by in-flows and a later out-flow, such as may be
required in the case of land reclamation by a mining firm);
• However, the IRR Method does have one significant
advantage -- managers tend to better understand the concept
of returns stated in percentages and find it easy to compare
to the required cost of capital; and, finally,
• While both the NPV Method and the IRR Method are both DCF
models and can even reach similar conclusions about a single
project, the use of the IRR Method can lead to the belief
that a smaller project with a shorter life and earlier cash
inflows, is preferable to a larger project that will
generate more cash.
| Is This Answer Correct ? | 24 Yes | 2 No |
Answer / ricky briones
The NPV is net present value. it place when the cost of
capital is known.
The IRR is internal rate of return. It place when the cost
of capital is unknown.
| Is This Answer Correct ? | 23 Yes | 17 No |
What is mean by Reserve on Consolidation?
3. In reviewing Corporate equity on a balance sheet, what effect be included in the description “Total Capital Stock” a) Par value of preferred b) Par value of common c) Paid in Capital excess of par value d) Both (a) and (b)
What is meant by the word Liquidation. Give examples
EXPAND___________LMB
A CAR GIVES 100 KLIO METERS OF TO
can we get all interview questions with answers in tally 9 which mostly asked in MNC's.
kindly given the example of contingent liabilities.
Define capital
deferred revenue expenditure
Dear All, Could any body send me the format of Delivery Challan? What is Even Transfer and Branch Transfer?Please let me know if any body knows? ekathirvel@gmail.com
What is Suspense Account?
When we issue credit note for free goods charged in invoice, whether we claim sales tax from the dept.