Scenario:
--------
-- You are a project manager in a large software house of
375 staff in total. The company has been running for 5
years. The company has been CMM assessed at level 3. The
company has many external clients for whom it develops a
wide range of business applications.
-- Most of the company‘s applications are developed in
Java. The waterfall lifecycle development model is normally
used in developments.
-- The company has historically suffered from the type of
problems that are common in the software industry. In
particular systems have been delivered not always to user
requirements and containing faults. The managing director
of the company is very keen for improvements to be made in
these areas.
-- You are in charge of a project team of 8 developers, 2
requirements engineers and 3 testers. Your team is just
about to start a new development.
System to Develop :( Exact Question )
-------------------------------------
-- Your team is about to start to develop a novel vehicle
navigation system for physically impaired drivers. The
navigation system not only identifies the correct route for
the driver in the normal way, but also controls the
steering wheel to navigate the car to the destination
identified by the driver.
-- A basic statement of requirements has been received from
the customer and budget and timescales have been formalised
into a contract.
Requires TASK to write :
------------------------
-- You must write a short report (maximum of 1 page) for
the managing director of your company outlining how you
propose to ensure that this project improves on previous
projects in terms of delivering to user requirements and
without faults. Your report must include how you propose to
show improvement on these issues to your managing director.
Also please tell me how should I choose the best software
model when given scenarios like these ...?
Answer / deepak chaudhury
The question has two parts, First about the standard
problem that the company has faced in its previous projects
and recommended solutions report. And the Second part about
the model that is a best fit for this kind of project,
First Part
----------------
From a PM's point of view the problem is, "Deliverables not
meeting the requirements / specifications or containing
faults". These problem happen mostly when, 1. the project
Scope is not clear, 2. when the requirement gathering
process is not clear or robust or is ambiguous, 3. when
there is no Change Management in place to track how the
requirements have changed over the life-cycle of the
project, 4. when product/project quality management is not
clear / not taken seriously.
Hence in your report mention clearly how you are planning
to tackle these four areas and explain how that will make
sure the deliverables are as per specification and will be
with minimal faults.
Second Part
----------------
For a project like this I will prefer a "protoyping" method
or an "agile" method as both of them follow the same method
to create a "complete Functional Model" first and then go
for the next step dpending on the findings from the
proptotype's behaviour and functionality. This is as per my
experience and can be different from what you might think
or plan in this scenario.
Thanks
Deepak Chaudhury, PMP
Is This Answer Correct ? | 8 Yes | 2 No |
What is the project management structure in your project? Is a PL assigned to the project?
What are the two data table in Microsoft Project 2007?
Explain the various activities you do (as a PL) when the project is started up.
How would you deal with a bug that no one wants to fix? Both the SDE and his lead have said they won?t fix it?
How do you assign tasks to your team members?
About current project architecture ?
Please, i am a final year student in nigeria and i have a project on pension fund administration and i need help in starting.
How do you report the status of your project?
When do revise your project plan? When do you know you have to revise your project plan? Where is the plan revision frequency documented?
What is your role in the current project and what kinds of responsibilities you are handling ?
8 Answers Infosys, Iron Mountain, Wipro,
Scenario: -------- -- You are a project manager in a large software house of 375 staff in total. The company has been running for 5 years. The company has been CMM assessed at level 3. The company has many external clients for whom it develops a wide range of business applications. -- Most of the company‘s applications are developed in Java. The waterfall lifecycle development model is normally used in developments. -- The company has historically suffered from the type of problems that are common in the software industry. In particular systems have been delivered not always to user requirements and containing faults. The managing director of the company is very keen for improvements to be made in these areas. -- You are in charge of a project team of 8 developers, 2 requirements engineers and 3 testers. Your team is just about to start a new development. System to Develop :( Exact Question ) ------------------------------------- -- Your team is about to start to develop a novel vehicle navigation system for physically impaired drivers. The navigation system not only identifies the correct route for the driver in the normal way, but also controls the steering wheel to navigate the car to the destination identified by the driver. -- A basic statement of requirements has been received from the customer and budget and timescales have been formalised into a contract. Requires TASK to write : ------------------------ -- You must write a short report (maximum of 1 page) for the managing director of your company outlining how you propose to ensure that this project improves on previous projects in terms of delivering to user requirements and without faults. Your report must include how you propose to show improvement on these issues to your managing director. Also please tell me how should I choose the best software model when given scenarios like these ...?
Q1. A. How can we determine performance standards? B. Write note on chaining views. Q2. A. Discuss the working with task in Gantt chart view. B. Explain the creation project schedule. Q3. A. What is understand in resource tracking? B. Write short notes on Caturing Baseline. Q4. A. How to customize workgroup message? B. How to use hyperlink? Q5. A. Explain the installation of project server? B. Discuss the working with to-do lists. Q6. A. Explain the working of templates? B. What is visual basic? C. Write shortnotes on user forms.