After you have completed the first phase of running
the 'Test Cases' in TD, now that you have set the status of
each step as Pass/Fail. How will you run the same 'Test
Cases' for regression testing (say for 2rd or 3th build)?
Answers were Sorted based on User's Feedback
Answer / ashish
Instead of going for new runs on existing test cases, I
will go for a new Test Set and add the required test cases
from to be regressed from the Test Plan. The new test set
can be named as 'build <number>'.
Is This Answer Correct ? | 4 Yes | 0 No |
Answer / laks
I think the use of 'Test Builder' comes into use for
regression and smoke testing.
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / sj1234
When YOu want to execute the Test-Cases for the 2nd or 3rd
Build take a new run.
So the status of old one is saved
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / vijaya
you can re run test cases on already run cases. The status
of previous runs can be checked by looking into history
Is This Answer Correct ? | 0 Yes | 0 No |
After creating the test cases in excel and exported to td. How does test director know the headings?
what is RTM in test director?
Can you please explain the procedure of connecting testdirector in qtp?
how do you integrate Perl or shell automation scripts in TD?
In the defect life cycle, if you find a defect in QC and think that it is not a valid defect. what will you do? just close it or store it in any document for future review, if yes what type of document and where?
what are the new versions in quality center,qtp?
Explain about user authentication in TD related to OS?
How do we write test cases for IVR(internet voice response).
Hi Can anyone tell the real time usage of Test director with examples u had done in u r company
What is Test case coverage? Skjha2000@rediffmail.com
3 Answers Infeneon Technologies,
Explain about failure options in TD
What is the role of snap shot in Test Director?