You are a project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements, because the poles are not buried to the correct depth. Which of the following is true?
A. You are in the Quality Assurance process and have performed a quality audit to assure correctness of work.
B. You are in the Scope Verification process and have performed a quality audit to assure correctness of work.
C. You are in the Contract Administration process and have completed a contract audit to assure the subcontractor's performance meets the contract requirements.
D. You are in the Performance Reporting process and have completed a performance review of the contractor's work.
No Answer is Posted For this Question
Be the First to Post Answer
You know that change control systems are important as they describe how to submit change requests and document how to manage the change, track the status, and determine the management impacts of the change. Each of the following processes in the Controlling process group uses a change control system as one of its tools and techniques except: A. Integrated Change Control B. Quality Control C. Scope Change Control D. Schedule Control
You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketing people are absolutely crazy about its potential. The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement. As the project manager, you know that a change has occurred to the project scope. Which of the following is true? A. Project scope changes do not require CCB approval. B. Performance measurement baselines are affected by scope changes. C. Project scope change uses inspection to determine if change has occurred. D. Project scope change uses workarounds to correct unexpected problems with scope change.
What is the key activity during Contract Closeout and Administrative Closure? A. Documenting lessons learned B. Creating project archives C. Disseminating information to formalize project closure D. Documenting project closure
You are ready to perform the Activity Sequencing process for your project. To make your job easier, you're going to use a software tool to help you draw a PDM network diagram. Most software programs use this technique. You know all of the following are true regarding the PDM except: A. It shows the activities on arrows and connects them to dependencies usually depicted as circles. B. It’s also called AON. C. It shows the activities in boxes with arrows connecting the dependent activities. D. It uses four types of dependency relationships of which finish to start is one.
You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. You adjust the schedule and find that two activities previously scheduled to start sequentially can be started at the same time. This is an example of: A. Crashing B. Fast tracking C. Resource leveling D. Adjusting the resource calendar
Describe size oriented metrics.
You are a project manager responsible for the construction of a new office complex. You are taking over for a project manager who recently left the company. The prior project manager completed the project charter and the scope statement for this project. In your interviews with some key stakeholders, you conclude that the scope statement was poorly constructed. You know all of the following are true except: A. It will be difficult to assess future project decisions from this scope statement. B. It will be difficult to decompose the deliverables from this scope statement. C. It will be difficult to assess cost and time estimates from this scope statement. D. It will be difficult to create an accurate WBS from this scope statement.
Your company has asked you to be the project manager for the product introduction of their new DeskTop Rock media system. You recently published the scope statement and the supporting detail. The supporting detail contains all of the following except: A. Constraints B. Other project information not noted in the scope statement C. Code of accounts D. Assumptions
Which of the following are the tools and techniques of the Cost Budgeting process? A. Project management information system, analogous estimating, bottom-up estimating, mathematical analysis B. Analogous estimating, bottom-up estimating, mathematical analysis, computerized tools C. Project management software, analogous estimating, bottom-up estimating, parametric modeling D. Analogous estimating, bottom-up estimating, parametric modeling, computerized tools
All of the following are true regarding the project plan except: A. Some of its inputs are outputs from other Planning processes. B. It's used to guide the project executing and controlling processes and is the baseline used to measure project performance. C. It consists of one document that should be formally approved and signed by stakeholders. D. It contains things like the WBS, project schedule, and resource assignments.
You are a project manager for Capella Systems. Your company writes custom software for accounting and financial systems for medium- to large-sized corporations. Your recent project has experienced some setbacks, and you've been forced to rework the design of one of the programs because it doesn't match the customer's requirements. Since some parts of the program have already been written, it will have to be rewritten so that it matches the design changes. This rework has increased costs, and you're beginning to notice some signs of poor morale because of the rework. Which of the following is true? A. The problems occurred because the WBS was not constructed properly. B. The quality assurance plan was carried out correctly, which is how the design problems were discovered. C. The problems occurred as a result of poor scope definition. D. The Risk Management Planning process details these kinds of risks and the responses you should put into place should they occur.
Which of the following processes involves receiving bids and proposals and applies evaluation criteria to the proposals to rank order the sequence of award? A. Contract Administration B. Procurement C. Source Selection D. Solicitation