You are the newly appointed project manager for a pharmaceutical company. Your company has asked you to head up a project to research a new children's medication. You've identified the lab equipment you'll need, the software needed to perform analysis and measurements, and the skill level and types of the technicians and researchers for this project. Which of the following is true?
A. The project manager and resources have been identified as part of the outputs of the Initiation process, and this information can be found in the project charter.
B. The resources and project manager have been identified as an input to the project Initiation phase. Further information is needed to produce the project charter, which will include the resources and project manager.
C. The project manager and resources have been identified as part of the project selection process. The selection committee requires resource information to make a final decision.
D. The resources and project manager have been identified as part of the project selection process. The selection committee requires resource information to make a final decision.
No Answer is Posted For this Question
Be the First to Post Answer
Which of the following are the tools and techniques of the Cost Budgeting process? A. Project management information system, analogous estimating, bottom-up estimating, mathematical analysis B. Analogous estimating, bottom-up estimating, mathematical analysis, computerized tools C. Project management software, analogous estimating, bottom-up estimating, parametric modeling D. Analogous estimating, bottom-up estimating, parametric modeling, computerized tools
You are the project manager for a construction company that is building a new city and county office building in your city. Your CCB recently approved a scope change. You know that scope change might come about as a result of all of the following except: A. Schedule revisions B. Product scope change C. Changes to the agreed-upon WBS D. Changes to the project requirements
Which of the following is true regarding the Resource Planning process? A. Resource Planning involves the human resource aspect of planning only, and its output is staffing requirements. B. Resource Planning involves the human resource aspect of planning only, and its output is staffing requirements. C. Resource Planning encompasses all the physical resources needed for the project, and its output is staffing requirements. D. Resource Planning encompasses all the physical resources needed for the project, and its output is resource requirements.
You are the project manager for a construction company that is building a new city and county office building in your city. You recently looked over the construction site to determine if the work to date was conforming to the requirements and quality standards. Which tool and technique of Quality Control are you using? A. Performance measurements B. Inspection C. Sampling D. Prevention
All of the following are true regarding the tools and techniques of Activity Sequencing except: A. GERT uses analogous methods. B. GERT allows for loops. C. GERT is a conditional diagramming method. D. GERT allows for conditional branches.
What are the inputs to the Initiation process? A. Product description, strategic plan, project selection criteria, and historical information B. Product description, strategic plan, project overview document, and historical information C. Strategic plan, project overview document, feasibility study, and historical information D. Product description, strategic plan, constraints, and assumptions
All of the following are true regarding the ADM method except: A. It's a tool and technique of Activity Sequencing. B. It uses one time estimate to determine durations. C. It's also called AOA. D. It's rarely used today.
Which of the following contracts should you use for projects that have a degree of uncertainty and require a large investment early in the project life cycle? A. Fixed price B. Cost reimbursable C. Lump sum D. Unit price
You are the project manager for Heartthrobs by the Numbers Dating Services. You're working on an updated Internet site that will display pictures as well as short bios of prospective heartbreakers. You've just completed your project staff assignments and published the project team directory. Which process are you in? A. Resource Planning B. Organizational Planning C. Project Development Planning D. Staff Acquisition
Write about organising and staffing in management.
0 Answers Mahatma Gandhi University,
Your company. Kick That Ball Sports, has appointed you project manager for their new Cricket product line introduction. This is a national effort, and all the retail stores across the country need to have the new products on the shelves before the media advertising blitz begins. The product line involves three new products, some with multiple deliverables. The Scope Definition process is now complete. Which of the following is true? A. The WBS template, an output of the Scope Definition process, was used from the previous project to create the WBS for this project. The WBS encompasses the major deliverables for the project. B. The WBS template from the previous project, an output from the Scope Planning process, was used to create the WBS for this project. The WBS encompasses the major deliverables for the project. C. The WBS, an output of the Scope Planning process, has been created, and it encompasses the full scope of work for the project. D. The WBS, an output of the Scope Definition process, has been created, and it encompasses the full scope of work for the project.
Which of the following is displayed as an S-curve? A. Gantt B. Cost baseline C. Critical path D. PERT