The Project Integration Management knowledge area is made up of which of the following processes?
A. Initiation, Project Plan Development, and Integrated Change Control
B. Project Plan Development, Project Plan Execution, and Integrated.
C. Project Plan Development, Initiation, and Scope Planning
D. Initiation, Scope Planning, and Integrated Change Control


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

You are the project manager for Changing Tides video games. You have produced a project network diagram and have updated the activity list. Which process have you just finished? A. The Activity Sequencing process, which identifies all the specific activities of the project B. The Activity Sequencing process, which identifies all the activity dependencies C. The Activity Duration Estimating process, which diagrams project network time estimates D. The Activity Duration Estimating process, which identifies all the dependent activities of the project

0 Answers  


The primary function of the Closing process is to: A. Formalize lessons learned and distribute this information to project participants B. Perform audits to verify the project results against the project requirements C. Formalize project completion and disseminate this information to project participants D. Perform post-implementation audits to document project successes and failures

0 Answers  


What are the tools for process improvement?

0 Answers  


Which performance measurement is the cost of work budgeted for an activity within a certain time frame? A. AV B. PV C. EV D. EAC

0 Answers  


As a project manager, you know that the most important activity to ensure customer and stakeholder satisfaction is which of the following: A. Documenting the requirements B. Documenting the performance measurements C. Reporting changes and updating the project plan and other project documents where appropriate D. Reporting project status timely and regularly

0 Answers  






Which of the following processes serve as inputs to each other? A. Executing and Controlling B. Planning and Executing C. Planning and Controlling D. Executing and Initiation

0 Answers  


All of the following are true regarding the project plan except: A. Some of its inputs are outputs from other Planning processes. B. It's used to guide the project executing and controlling processes and is the baseline used to measure project performance. C. It consists of one document that should be formally approved and signed by stakeholders. D. It contains things like the WBS, project schedule, and resource assignments.

0 Answers  


Which logical relationship does the PDM use most often? A. Start to finish B. Start to start C. Finish to finish D. Finish to start

0 Answers  


What are the different types of software risks?

0 Answers  


You are a project manager for Penguin Software. Your company creates custom software programs for hospitals and large dental offices. You have just completed a project and are performing earned value analysis, trend analysis, and performance reviews. Which of the following is true? A. This is performance measurement documentation, which is an input to the Contract Closeout process B. This is performance measurement documentation, which is an input to the Administrative Closure process C. These are performance reporting tools and techniques of the Administrative Closure process D. These are performance reporting tools and techniques of the Contract Closeout process

0 Answers  


You are working on a project that will upgrade the phone system in your customer service center. You have used bottom-up estimating techniques to assign costs to the project activities and have determined the cost baseline. Which of the following is true? A. You have completed the Cost Estimating process and now need to complete the Cost Budgeting process to determine the project's baseline. B. You have completed the Project Plan Development process and established a project baseline to measure future project performance against. C. You have completed the Cost Estimating process and now need to complete the Project Plan Development process to establish a project baseline to measure future project performance against. D. You have completed the Cost Budgeting process, and the cost baseline will be used to measure future project performance.

0 Answers  


Performance reporting tools and techniques include all of the following except: A. Earned value analysis B. Statistical sampling C. Variance analysis D. Performance reviews

0 Answers  


Categories