What is the difference between risk impact and risk probability?
No Answer is Posted For this Question
Be the First to Post Answer
Ruby is an administrative assistant with another department. Her manager has agreed to loan Ruby's services to you on a part-time basis during your current project. Ruby is putting together the cost projections you've gathered so far. You want to include these costs in the project charter. Ruby is formatting this information for you into a spreadsheet package and is printing copies. Which of the following is true? A. All of the costs, including Ruby's time, are charged to the project. B. All of the costs, Ruby is typing into the spreadsheet are project costs. Ruby's time is not directly related to the project and should not be included. C. The project costs, including Ruby's time, should be included in the project charter. D. The project costs, excluding Ruby's time, should be considered project constraints.
Explain the Principals of Management
0 Answers Mahatma Gandhi University,
You are a project manager for a network cabling project for your organization. Your project team is made up of six full-time employees and three contractors. This is the first time they have all worked together. This project requires accurate information exchange at all times during the life of the project. How many lines of communication exist among the project team members? A.36 B.41 C.18 D.34
This measurement is the value of the work that's been completed to date: A. PV B. AC C. EV D. EAC
You are a project manager for a manufacturing firm that produces Civil War-era replicas and memorabilia. You discover a design error during a test production run on your latest project. Which of the following is the most likely response to this problem? A. Reduce the technical requirements so that the error is no longer valid. B. Go forward with production and ignore the error. C. Go forward with production but inform the customer of the problem. D. Develop alternative solutions to address the error.
You are project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements. All of the following are valid options except: A. You document the poor performance in written form and send the correspondence to the subcontractor change request through Contract Administration. B. You terminate the contract for poor performance and submit a change request through Contract Administration. C. You submit a change request through Contract Administration to ask the subcontractor to comply with the terms of the contract. D. You agree to meet with the subcontractor to see if a satisfactory solution can be reached.
what do u mean by an interview? no explanations but define.
Your project is in the Scope Definition process. You've just completed the WBS. Which of the following is true? A. The WBS breaks the project deliverables down to a level where alternatives identification can be used to determine how level two assignments should be made. B. The WBS breaks the project deliverables down to a level where project constraints and assumptions can be easily identified. C. The WBS breaks the project deliverables down to the work package level where product analysis can be documented. D. The WBS breaks the project deliverables down to the work package level where cost and time estimates can be easily determined and quality control measurements can be determined.
Which of the following might require rebaselining of the cost baseline? A. Corrective action B. Revised cost estimates C. Updates to the cost management plan D. Budget updates
How does a project manager can avoid the above given ten points for the success of project.
Your project depends on a key deliverable from a vendor you've used several times before with great success. You're counting on the delivery to arrive on June 1. This is an example of : A. Constraint B. Objective C. Assumption D. Goal
How project comes to a software company? what is the role of sales department,marketing department,delivery manager,project manager in a software development? simply,what is project life cycle?