Explain the difference between Project management and IT management.
No Answer is Posted For this Question
Be the First to Post Answer
What are the 10 knowledge areas of project management?
When a project is being performed under contract, the product description is provided by which of the following? A. The buyer B. The project sponsor C. The project manager D. The contractor
You are ready to perform the Activity Sequencing process for your project. To make your job easier, you're going to use a software tool to help you draw a PDM network diagram. Most software programs use this technique. You know all of the following are true regarding the PDM except: A. It shows the activities on arrows and connects them to dependencies usually depicted as circles. B. It’s also called AON. C. It shows the activities in boxes with arrows connecting the dependent activities. D. It uses four types of dependency relationships of which finish to start is one.
You are the project manager for Changing Tides video games. You have gathered the inputs for the Activity Duration Estimating process. You will employ which tools and techniques to produce the outputs for this process? A. Activity list, analogous estimating, quantitatively based durations, and alternatives identification B. Activity list, analogous estimating, expert judgment, and quantitatively based durations C. Expert judgment, analogous estimating, quantitatively based durations, and reserve time D. Expert judgment, alternatives identification, quantitatively based durations, and reserve time
You are developing your project schedule and have decided to use the PERT method to determine project duration. The estimates you've gathered so far include the following: Most likely is 200 hours, optimistic is 180 hours, and pessimistic is 220 hours. Which of the following is the correct PERT estimate? A. 190 B. 266 C. 200 D. 210
You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization's operating system on 236 servers. You performed this project under contract. You are in the Contract Closeout process and have reviewed the contracting process to identify lessons learned. What is the name of the tool and technique of Contract Closeout you used to perform this function? A. Procurement audits B. Performance reviews C. Performance audits D. Procurement reviews
The Project Integration Management knowledge area is made up of which of the following processes? A. Initiation, Project Plan Development, and Integrated Change Control B. Project Plan Development, Project Plan Execution, and Integrated. C. Project Plan Development, Initiation, and Scope Planning D. Initiation, Scope Planning, and Integrated Change Control
Which of the following processes serve as inputs to each other? A. Executing and Controlling B. Planning and Executing C. Planning and Controlling D. Executing and Initiation
Which of the following processes negotiates the sequence of award by rank ordering the proposals? A. Source Selection B. Solicitation C. Contract Administration D. Procurement
You are a project manager for a network cabling project for your organization. Your project team is made up of six full-time employees and three contractors. This is the first time they have all worked together. You know that the team will go through the stages of team development in the following order: A. Forming, storming, norming, and performing B. Storming, norming, forming, and performing C. Norming, storming, forming, and performing D. Forming, norming, storming, performing
What are the tools for process improvement?
You’re promised your team two days of paid time off plus a week’s training in the latest technology of their choice if they complete their project ahead of schedule. This is an example of which of the following? A. Achievement theory B. Expectancy theory C. Maslow's theory D. Contingency theory