How do you handle conflicts in the Team Management ?


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

This process applies evaluation criteria to the bids and proposals received from potential vendors: A. Solicitation B. Contract Administration C. Source Selection D. Quality Assurance

0 Answers  


What are the framework activities and umbrella activities?

0 Answers  


You are a project manager for Uncle Sam's Flag Company. Your company has designed a new line of products featuring the American flag. Due to some unique circumstances, the products are in hot demand and the project sponsor has asked you to do whatever it takes to get this project completed early and make the products available. You are to add resources to the project. The sponsor agrees to pay the additional costs since time is now a critical factor. Which technique have you used? A. Crashing B. Resource leveling C. Fast tracking D. Resource loading

0 Answers  


How to deal with underperforming team members?

0 Answers  


You are the project manager for your company's annual Spring Fling. You've made all the plans and reserved the outdoor grounds for the appropriate day and time. You are now two days away from the big day, and the forecast is calling for light rain showers in the afternoon. You rented tents just in case this risk occurred. This is an example of which Risk Response Planning tool and technique? A. Passive acceptance B. Contingency planning C. Avoidance D. Transference

0 Answers  






Which of the following is true regarding the critical path? A. It should never be compressed. B. It allows for looping and branching. C. The critical path technique is the same as PERT. D. It's the duration of all tasks with zero float.

0 Answers  


What are the outputs of the Scope Planning process? A. Product analysis, scope statement, and scope management plan B. Scope statement, scope management plan, and WBS C. Scope statement, supporting detail, and WBS D. Scope statement, supporting detail, and scope management plan

0 Answers  


Your project has recently experienced change. Some of the agreed-upon WBS elements have been changed as a result. What kind of change has occurred? A. Schedule change B. Risk response change C. Quality change D. Scope change

0 Answers  


Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. Which of the following is true? A. You document the circumstances as lessons learned. B. You pay particular attention to archiving the financial records for this project. C. Your project ended due to starvation because of the cost overruns. D. You document the circumstances surrounding the project completion during the Scope Verification process.

0 Answers  


you are the project manager of a project , customer is asking for a change in scope and agrees that it will be a CR. But you do not want to take the CR for whatever reason. How will you convince the customer in doing so

2 Answers   Samsung, Wipro,


How will you measure software quality?

0 Answers  


Which of the following might require rebaselining of the cost baseline? A. Corrective action B. Revised cost estimates C. Updates to the cost management plan D. Budget updates

0 Answers  


Categories