Answer / janaki ram
In Royce's original waterfall model, the following phases
are followed in order:
1. Requirements specification
2. Design
3. Construction (AKA implementation or coding)
4. Integration
5. Testing and debugging (AKA validation)
6. Installation
7. Maintenance
Is This Answer Correct ? | 6 Yes | 3 No |
Answer / ramesh naidu m
Water fall model one of development methodalogy , in which
all the reqirements are freezed before begining the SDLC
Aassuming there won't be any changes in future.If at all
they come they will treat it as enhancement and they will
have a fixed time frame to finish and close the project.For
kind of small projects they will use this methodalogy.
Is This Answer Correct ? | 2 Yes | 1 No |
Tell me difference between sap bi & business object dw/ reporting?
You run a technical support website where members post questions and answers to problems experienced and general know how. You have to provide explanations to recently posted questions. Some opf these questions need reasearch.
difference between SAP BI & business object DW/ reporting
DIFFERENCE BETWEEN RELEASE AND VERSION???
Why is it that hot water in a hotel comes out instantly but at home it takes time?
Who reviews the requirements and the changes to the requirements?
You run a technical support website where members post questions and answers to problems experienced and general know how. You have to provide explanations to recently posted questions. Some opf these questions need reasearch.
LEARN SAP FROM REAL TIME CONSULTANT Dear all, this is rajan,working as a SAP HR CONSULTANT, I am worked as also a corporate trainer, now I use to take online class. If u r really interested to learn sap the real time configuration,pl directly contact me. here u will be getting real time knowledge, So if u r really carrier oriented and want to make carrier in sap contact me Rajan 9986213471 bangalore
If during some stage down the life cycle, the initial requirements change, what will you do? How will you handle any changes in the requirements?
What will you do if you find that you cannot meet the requirements?
There are 3 ants at 3 corners of a triangle, they randomly start moving towards another corner. What is the probability that they don't collide?
What is your project about? What stage or phase is it currently in? What is your current role in your project?