Answer / fred
Let us say:
Electricity unit=kwh
Cost = USD/m3
Assuming:
Your Mixing Concrete Plant can produce 100m3 in 1hrs and the consumption electricity is 10 kwh, the cost per kwh is 10 USD.
Therefore:
100 m3/hr = 100 USD
| Is This Answer Correct ? | 0 Yes | 1 No |
how could you change gas line control valve to liquid line valve?
what is the electronic presipitator ?
What is the difference between predictive-maintenance and proactive-maintenance?
what is fixed bearing?
Why virtual corporation is used?
whats te normal transformer current rating
where is fixed bearing located?
What is the purpose of departmental classification?
how can we choose the controller of CNC bending machine?and how can we know the nomber of the machine axis?
Explain about fire hydrant and its related water pressures?
What is autofacturing?
What is difference between Hazard & Risk
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)