An enterprise has established a steering committee to
oversee its e-business program. The steering committee would
MOST likely be involved in the:
A. documentation of requirements.
B. escalation of project issues.
C. design of interface controls.
D. specification of reports.
Answer / guest
Answer: B
The function of the steering committee is to ensure the
success of the project. If there are factors or issues that
potentially could affect planned results, the steering
committee should escalate them. Activities such as
documentation of requirements, design of interface controls
and specification of reports are the responsibility of the
project team.
Is This Answer Correct ? | 5 Yes | 0 No |
After a full operational contingency test, the IS auditor performs a review of the recovery steps and concludes that the elapsed time until the technological environment and systems were actually functioning, exceeded the required critical recovery time. Which of the following should the auditor recommend? A. Perform an integral review of the recovery tasks. B. Broaden the processing capacity to gain recovery time. C. Make improvements in the facility's circulation structure. D. Increase the amount of human resources involved in the recovery.
Which of the following imaging technologies captures handwriting from a preprinted form and converts it into an electronic format? A. Magnetic ink character recognition (MICR) B. Intelligent voice recognition (IVR) C. Bar code recognition (BCR) D. Optical character recognition (OCR)
A digital signature contains a message digest to: A. show if the message has been altered after transmission. B. define the encryption algorithm. C. confirm the identity of the originator. D. enable message transmission in a digital format.
Which of the following forms of evidence for the auditor would be considered the MOST reliable? A. An oral statement from the auditee B. The results of a test performed by an IS auditor C. An internally generated computer accounting report D. A confirmation letter received from an outside source
Which of the following would normally be found in application run manuals? A. Details of source documents B. Error codes and their recovery actions C. Program flowcharts and file definitions D. Change records for the application source code
Which of the following is a benefit of a risk-based approach to audit planning? Audit: A. scheduling may be performed months in advance. B. budgets are more likely to be met by the IS audit staff. C. staff will be exposed to a variety of technologies. D. resources are allocated to the areas of highest concern.
An IS auditor reviewing an outsourcing contract of IT facilities would expect it to define the: A. hardware configuration. B. access control software. C. ownership of intellectual property. D. application development methodology.
Which of the following reports should an IS auditor use to check compliance with a service level agreement (SLA) requirement for uptime? A. Utilization reports B. Hardware error reports C. System logs D. Availability reports
Which of the following is necessary to have FIRST in the development of a business continuity plan? A. Risk-based classification of systems B. Inventory of all assets C. Complete documentation of all disasters D. Availability of hardware and software
Which of the following techniques would provide the BEST assurance that the estimate of program development effort is reliable? A. Function point analysis B. Estimates by business area C. A computer-based project schedule D. An estimate by experienced programmer
Which of the following facilitates program maintenance? A. More cohesive and loosely coupled programs B. Less cohesive and loosely coupled programs C. More cohesive and strongly coupled programs D. Less cohesive and strongly coupled programs
While reviewing an ongoing project, the IS auditor notes that the development team has spent eight hours of activity on the first day against a budget of 24 hours (over three days). The projected time to complete the remainder of the activity is 20 hours. The IS auditor should report that the project: A. is behind schedule. B. is ahead of schedule. C. is on schedule. D. cannot be evaluated until the activity is completed.