Which of the following reports is a measure of
telecommunication transmissions and determines whether
transmissions are completed accurately?
A. Online monitor reports
B. Downtime reports
C. Help desk reports
D. Response time reports
Answer / guest
Answer: A
"Online monitors measure telecommunication transmissions and
determine whether transmissions are completed accurately.
Downtime reports track the availability of telecommunication
lines and circuits
help desk reports handle problems occurring in the normal
course of operations
and response time reports identify the time it takes for a
command entered at a terminal to be answered by the computer."
| Is This Answer Correct ? | 4 Yes | 0 No |
Controls designed to ensure that unauthorized changes are not made to information residing in a computer file are known as: A. data security controls. B. implementation controls. C. program security controls. D. computer operations controls.
Which of the following would an IS auditor consider to be the MOST helpful when evaluating the effectiveness and adequacy of a computer preventive maintenance program? A. A system downtime log B. Vendors' reliability figures C. Regularly scheduled maintenance log D. A written preventive maintenance schedule
Which of the following is the MOST likely reason why e-mail systems have become a useful source of evidence for litigation? A. Multiple cycles of backup files remain available. B. Access controls establish accountability for e-mail activity. C. Data classification regulates what information should be communicated via e-mail. D. Within the enterprise, a clear policy for using e-mail ensures that evidence is available.
A decision support system (DSS): A. is aimed at solving highly structured problems. B. combines the use of models with nontraditional data access and retrieval functions. C. emphasizes flexibility in the decision making approach of users. D. supports only structured decision-making tasks.
An organization acquiring other businesses continues using its legacy EDI systems, and uses three separate value added network (VAN) providers. No written VAN agreements exist. The IS auditor should recommend that management: A. obtain independent assurance of the third party service providers. B. set up a process for monitoring the service delivery of the third party. C. ensure that formal contracts are in place. D. consider agreements with third party service providers in the development of continuity plans.
The PRIMARY objective of conducting a post-implementation review is to assess whether the system A) achieved the desired objectives B) provides for backup and recovery C) provides for information security D) documentation is clear and understandable
Which of these has the potential to improve security incident response processes? A. Review the incident response procedures. B. Post-mortem or post-event reviews by the security team. C. Getting the hot-site ready. D. Reviw the BCP plan every six months
The BEST time to perform a control self-assessment involving line management, line staff and the audit department is at the time of: A. compliance testing. B. the preliminary survey. C. substantive testing. D. the preparation of the audit report.
To develop a successful business continuity plan, end user involvement is critical during which of the following phases? A. Business recovery strategy B. Detailed plan development C. Business impact analysis D. Testing and maintenance
Which of the following offsite information processing facility conditions would cause an IS auditor the GREATEST concern? The facility A. is identified clearly on the outside with the company name. B. is located more than an hour driving distance from the originating site. C. does not have any windows to let in natural sunlight. D. entrance is located in the back of the building rather than the front.
During an audit of the tape management system at a data center, an IS auditor discovered that parameters are set to bypass or ignore the labels written on tape header records. The IS auditor also determined that effective staging and job setup procedures were in place. In this situation, the IS auditor should conclude that the: A. tape headers should be manually logged and checked by the operators. B. staging and job setup procedures are not appropriate compensating controls. C. staging and job setup procedures compensate for the tape label control weakness. D. tape management system parameters must be set to check all labels.
At the end of the testing phase of software development, an IS auditor observes that an intermittent software error has not been corrected. No action has been taken to resolve the error. The IS auditor should: A. report the error as a finding and leave further exploration to the auditee's discretion. B. attempt to resolve the error. C. recommend that problem resolution be escalated. D. ignore the error, as it is not possible to get objective evidence for the software error.