When a systems development life cycle (SDLC) methodology is
inadequate, the MOST serious immediate risk is that the new
system will:
A. be completed late.
B. exceed the cost estimates.
C. not meet business and user needs.
D. be incompatible with existing systems.
Answer / guest
Answer: C
Although all of the answers are risks of an inadequate SDLC
methodology, the first and most devastating is that the new
system will not need business and user needs and requirements.
| Is This Answer Correct ? | 10 Yes | 1 No |
Which of the following provides nonrepudiation services for e-commerce transactions? A. Public key infrastructure (PKI) B. Data encryption standard (DES) C. Message authentication code (MAC) D. Personal identification number (PIN)
Which of the following MUST exist to ensure the viability of a duplicate information processing facility? A. The site is near the primary site to ensure quick and efficient recovery. B. The site contains the most advanced hardware available. C. The workload of the primary site is monitored to ensure adequate backup is available. D. The hardware is tested when it is installed to ensure it is working properly.
Good quality software is BEST achieved: A. through thorough testing. B. by finding and quickly correcting programming errors. C. determining the amount of testing by the available time and budget. D. by applying well-defined processes and structured reviews throughout the project.
A vendor/contractor?s performance against service level agreements must be evaluated by the: A. customer. B. contractor. C. third-party. D. contractor?s management.
Which of the following hardware devices relieves the central computer from performing network control, format conversion and message handling tasks? A. Spool B. Cluster controller C. Protocol converter D. Front end processor
In a risk-based audit approach, an IS auditor, in addition to risk, would be influenced by: A. the availability of CAATs. B. management's representation. C. organizational structure and job responsibilities. D. the existence of internal and operational controls
Which of the following is an implementation risk within the process of decision support systems? A. Management control B. Semistructured dimensions C. Inability to specify purpose and usage patterns D. Changes in decision processes
The PRIMARY reason for replacing checks (cheques) with EFT systems in the accounts payable area is to: A. make the payment process more efficient. B. comply with international EFT banking standards. C. decrease the number of paper-based payment forms. D. reduce the risk of unauthorized changes to payment transactions.
Which of the following is MOST likely to result from a business process reengineering (BPR) project? A. An increased number of people using technology B. Significant cost savings, through a reduction in the complexity of information technology C. A weaker organizational structures and less accountability D. Increased information protection (IP) risk will increase
An IS auditor conducting a review of disaster recovery planning at a financial processing organization has discovered the following: * The existing disaster recovery plan was compiled two years ago by a systems analyst in the organization's IT department using transaction flow projections from the operations department. * The plan was presented to the deputy CEO for approval and formal issue, but it is still awaiting his attention. * The plan has never been updated, tested or circulated to key management and staff, though interviews show that each would know what action to take for their area in the event of a disruptive incident. The basis of an organization's disaster recovery plan is to reestablish live processing at an alternative site where a similar, but not identical hardware configuration is already established. The IS auditor should: A. take no action as the lack of a current plan is the only significant finding. B. recommend that the hardware configuration at each site should be identical. C. perform a review to verify that the second configuration can support live processing. D. report that the financial expenditure on the alternative site is wasted without an effective plan.
When reviewing a business process reengineering (BPR) project, which of the following is the MOST important for an IS auditor to evaluate? A. The impact of removed controls. B. The cost of new controls. C. The BPR project plans. D. The continuous improvement and monitoring plans.
Large-scale systems development efforts: A. are not affected by the use of prototyping tools. B. can be carried out independent of other organizational practices. C. require that business requirements be defined before the project begins. D. require that project phases and deliverables be defined during the duration of the project.