what is the working principle of ABB gas analyser of kiln in cement industries..

Answer / bilal

O2 Analyzers Principle:- the basic principle of that
analyzer is Paramagnetic system its installed the coil and
when we need to measure the gas we generate the e.m.f Oxygen
elements drooped there then we measured the value.

Is This Answer Correct ?    17 Yes 3 No

what is the working principle of ABB gas analyser of kiln in cement industries..

Answer / bapun

The working principle of advanced optimum analyser is
different from the easy line gas analyser.

Is This Answer Correct ?    11 Yes 4 No

what is the working principle of ABB gas analyser of kiln in cement industries..

Answer / vijay krishna

for analysing the oxygen percentage in atmp ferromagnatism
principle is used.o2 consists of magnatism property when
ever the o2% will be less whaet bridge will be unbalanced
and give the signal.

Is This Answer Correct ?    8 Yes 4 No

what is the working principle of ABB gas analyser of kiln in cement industries..

Answer / shayan ali

In combination with the gas analyzer system the solution ensures effective monitoring of the primary and secondary combustion, validates the clinker quality, minimizes the fuel costs through optimized combustion control and supports a safe operation.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Instrumentation Interview Questions

how to measure flow with dp

1 Answers  


What types of thermocuple are mostly used?

6 Answers  


in my plant 100% feedwater control v/v is air to close but due to instrument air fail,the valve opens but instead of drum level high its get tripped in low low drum level.the urv of level tx is 0 and lrv is -800.pls tell me the reason. for such behaviour.

1 Answers   Sirpur Paper Mill,


Hi friends, from Aug 4th onwards iam getting spikes for analog inputs in our DCS for a period of 800ms. I throughly checked every thing, finally i found that the DI, DO's from MCC panels shields are terminated in the Signal Earth where Analog Input signals shields are terminated. Is there any problem with this type of termination?. i checked the induction voltage from MCC and getting around 25VAC, please suggest me in this concern. Our plant is 8months old only. DCS is Siemens Make Simatic PCS7, and the transmitters are Yokogawa make.

1 Answers  


what do you mean by smart instruments?explain with example

4 Answers  






Range 8 Kg/cm2, alarm to be set at 2Kg/cm2, at wat pressure reciever switch to be calibrated? justify the ans?

3 Answers  


Why flow/pressure transmitter before control valve?

0 Answers   UPL,


why temperature transmitter is showing ambienttemp.but 21.5ma. alarm AO showing at the display &how to sloves this problem.

2 Answers  


what are the documentation and instrument identification system used to identify the correct device to be calibrated? name atleast three.

1 Answers  


How can we measure the level of a closed system like drum

3 Answers  


IF TX SHOWS SLOW RESPONSE, WHILE A CLOSE LOOP AND WHEN WE PUT THE CONTROLLER ON MANUAL THE PROBLEM RECTIFIED, SO WE CAN SAY THE PROBLEM IS IN

1 Answers   IFFCO,


Can u tell me the principle of the tc,rtd,level switch,pressure switch ,transmitter(pr flow level temp.),vibration...plz

0 Answers   Adani, SRF,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)