When auditing the requirements phase of a system development
project, an IS auditor would:

A. assess the adequacy of audit trails.

B. identify and determine the criticality of the need.

C. verify cost justifications and anticipated benefits.

D. ensure that control specifications have been defined.

Answer Posted / guest

Answer: D

During the requirements phase the IS auditor should verify
the detailed requirements definition document. The IS
auditor would identify and determine the criticality of the
need and verify all cost justifications/benefits during the
feasibility phase. The assessment of the adequacy of audit
trails would take place during the detailed design and
programming phase.

Is This Answer Correct ?    5 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

purchase orders issued to vendors have been authorized as per the authorization matrix

1204


WHICH OF THE FOLLOWING IS OFTEN AN ADVANTAGE OF USING PROTOTYPING GOR DYDTEM DVELOPMENT

2975