Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to calculate busbar size & what is the procedure we
make for determine that?

Answer Posted / vijaykumarht

Depending on the maximum load current the busbar size will
be determined. Usually for copper it is taken as 2 to 4 Amps
per square mm and for alluminium it is taken as 1 to 2 Amps
per sqmm.
The normal availability and design of the busbars is
25*5mm,50*5mm,50*10mm,60*10mm.

Is This Answer Correct ?    57 Yes 61 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Initially, when the input is not equal to the output — what type of response is this?

1061


1.what is mean by 8/20 micro sec waveshape

2231


what is solkor relay and which condition it will act?

3360


What is ST and specify its range of voltage.

1976


How do you compute voltage drop and cable size over distance?

2271


Will an earth leakage trip be activated if the component or wiring is faulty on low voltage equipment.Example An electrical Cat Scarer placed in the garden and water gets into the wiring.

1864


Dyn1 transformer vector group testing how to do

1803


(1)The demand for electricity , the amount of renewable generation available, the amount of fossil fuel generation available and the cost of the fossil fuel generation are shown in table below period(hrs) demand(MW) renewable (MW) fossil- fuel(MW) cost of fossil fuel(MW) 00.00 - 01.00 2000 1800 2000 30 01.00 - 02.00 2300 2500 2000 30 02.00 - 03.00 2500 2700 2100 45 03.00 - 04.00 2900 3100 2100 50 04.00 - 05.00 2700 2600 2500 45 05.00 - 06.00 2400 2000 2700 50 06.00 - 07.00 2200 1800 2000 36 07.00 - 08.00 2100 1600 2000 36 Assuming that the renewable generation incurs zero cost, determine an optimal generation schedule(specifying the amount of renewable generation and fossil fuel generation used in each period, the cost for each period and the overall cost for 8 hours.)

1866


Write the analogous electrical elements in force current analogy for the elements of mechanical translational system.

1266


Why do we need interlocking in a HT metering or Ring main unit switchgear?

2026


Explain the experiment on ward leonard method of a speed control on a dc shunt motor with an suitable circuit diagram.

2589


why the India electrical supply transmission loss is high when compare to us

1979


what are the 4 rules to start the motor?

2122


CAN U PLEASE TELL ME SOME G.D TOPICS FOR APGENCO INTERVIEW&G.D

2408


what is saturation kit?which use above 15 kw motors panel side.

4201