What are the technical reasons for soaking transformers for
various times before allowing them to pick load after a
fault ?

Answer Posted / japjeev

The soaking process is to determine the sufficiency of the
cooling oil for continuous operation under temperature and
duty cycles.

If an outage occurs placing heavy load currents on a
transformer it must be assured that it will survive without
exploding, melt-down, etc

Is This Answer Correct ?    15 Yes 15 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

as a electrical student why should i hire you?

1984


If we need4× 50mm sq cable but it's not available so we can pull 4×25mm sq 2cables

906


Is it true online ups having bypass mode if it is true then why we called ups because it is interrupting power when goes in bypass mode

1549


what is the basic construction diffrance between servo motor ans sqiralcage induction motor

2018


what is the major difference between LIBBP & HIBBP.. which one is most preferable..

2028






harmonics filter

1518


How many types of interlocking use in screw type air compressor,make-Kaser(BSD MODEL)?

1605


what are the reasons of CT circuit faulty in busbar protection scheme?

963


why would the rotor rotate at sub synchronous speed against the direction of rotating flux when d rotor of 3 phase IM is connected to 3 phase balanced supply and the stator windings are shortcircuited ??

1533


what is meaning of 230volts ac 50hzs ac supply is it rms or maximum to getting ac 230v what amount of max voltage they will send

1553


what is earth pit , how we can measured it, what earth rods reference

2073


How can two 3 phase transformers of same KVA and Voltage be connected in parallel?

1346


What is the function of a neutral reactor.

1319


How to synchronization will be done between two DGs ?

1321


full form of flry b

3616