Answer Posted / madhusudhan
1+1+2=4
1/4=0.25x1440=360kg
Or 7.2bags per m³
For 1m³wet concrete you required 1.54x360kg=554.4kg cement
Or 11.088 bags
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
according to the painting co efficient, we should take the one side of doors (or) windows or both sides?
Cement consumption of one cubic meter of aerocon blocks masonry?
How do You Maintain a structure after getting cube test of low strength.
How to design 12*12*14 room having rrc slab ,coloum, beam,foundation?
Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day
SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?
What in your opinion makes you the most suitably qualified candidate for this post of civil engineering technician?
estimate quanitity of bricks(19x9x9cm without mortar), cement & sand in 10feet X 10feet wall ?
what is civil engineer greatest strength and weakness?
What is the difference between built area and super built up area?
how do we calculate quantity of cement sand and aggregates in 1m3 of m20 m25 grade concrete?
Can inverted beams used in pipes during construction? If yes, explain how it can be implemented?
Form where IS456 is adopted in 1978?
Which tests are performed on soil to decide the type of foundation to be provided.
Explain what is zoning permit?