what is the actual productivity of carpentor,fitter,masson
for brickwork and masson for plaster etc
Answer Posted / hari
1) 1m+1mh=10m2 blockwork per day
2)1m+1mh shuttering=around 5m2 per day
3)1m+1mh barbending=around 200kgs per day , inc cutting,bending,placing.
| Is This Answer Correct ? | 13 Yes | 4 No |
Post New Answer View All Answers
How to calculate 1 brss for RCC work
Define What is diversion tunnel in a dam?
how much quantity of cement,sand and water required for 1 sq feet flooring work .
What is binding spacing of the rebars at lapping zones.
Explain what is zoning permit?
For The preparation of goverment examination Which book i will prefer and by which way i will do the preparation for exam.
What do you mean by the word 'shear'?
Can compresive strength test for concrete at 1 day age possible to carry out? If yes, which IS code describes the procedure for such testing?
Slump Values for works?
How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 100 microns?
how to find quantity of concrete in PCC M15
how to calculate testing date
what is the difference between natural draught cooling tower and induced draught cooling tower
it is a corrected question." make a list of engineering property(properties) of soil.
Please tell me vasthu room sizes. Thanks.