Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how the find ct mf and mf roll in metering

Answer Posted / ravinder kumar

when the CT ratio & Meter CT Ratio is different then we have to multiply the meter reading by a factor i.e. called MF to find exact value.
MF= (field CTR*field PTR)/(meter CTR*meter PTR)

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

given data are load current & power factor cable core size? plz any one update the calculation formula

1938


700KW 6.6KV slip ring induction motor to use VFD to control the speed

3257


dear sir, i completed diploma in electrical in 2005, how i can get electrical supervisor liance in mumbai

2019


On a 6 KVA UPS we have to provide a DC MCB for Battery bank of 16 nos (12 V 42 AH). What Shall be the current rating of DC MCB ?

2718


What are the site acceptance tests for power cables, DG Sets, LT panels & 30kVA UPS ?

2439


which one is more efficient, torq, power & ecnomy with the same frame size AC motor / DC motor?

2237


how we start 40w tube light with 4 diodes,2capacitors,1 choke and without starter.(a product avilable in market which lights burnt tube lights also)

2104


Explain the operation carried out in thermal power stations?

1077


why asa method ZPF method is more accurate than ASA method?

5860


can any tell me why slope 40% and 80% is calculated in differential protection?

1940


How can calculate the rating of a alternator for a given specific load with formula

2425


Why do we need a separate control desk & PLC control panel in Boiler plant or coal handling plant? Can we provide cost effective Control desk cum PLC panel. Is there is an specific need for control desk.. kindly advice.

2430


What is the function of NGR for the parallel operation of alternator? whats happen when different rating of alternator are running with parallel?

3042


how to set the time in digital timer ?

2082


In the ACB breaker capacity is 2000Amp but this each phase taken 1250 But total beldibg load is 600amp or 700amp watt is the problem

2019