Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

Why short circuit calculation is not required in LT cable
sizing and requiredin HT cable sizing only

Answer Posted / sudhanva madhukar mahamuni

Generally LT Cable size are not calculated based on Fault current basis, Due to High Fault current on LT System. For e.g. consider that 2500 kVA Transformer, %Z = 6.25%, 415 Volts at Secondary. Fault Current at Secondary system will be 55.64 kA. Now if we would have to select the Cable size based on Fault current then it would be ---
If √t
A = ----------------- Sq.mm --- For XLPE Cable Aluminum Conductor
0.094

585 sqmm, nearest standard rating of cable is 630 sqmm. Hence Commercially as well as laying point of view the same is not recommended nor as per good engineering practice.

HT Cable Sizing :

Cable sizing based on Fault current is possible In HT System, based practically and commercially point of view. Consider that 11kV system is feeding the power supply. As per IS 2026, 11kV Power system will have max 500MVA Fault Level. It means it will have 26 kA. 300sqmm cable will be sufficient to withstand 26 kA for 1 Sec.

Summary : System Design shall not be strictly as norms, it should be design considering Laying / installation, Practically and Commercially viable.

Regards

Sudhanva Madhukar Mahamuni
electricmahamuni@gmail.com

Is This Answer Correct ?    2 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Can any one give an explanation about rating factors of cable? if we are laying the cable on the air with an temp 15 degree then rating factors will be 1.15 and if we are laying the cable on the air an temp 60 degree then rating factor will be 0.76 please describe it and what is the difference between rating factor and derating factor?

1429


what is KSR type transmission tower? What is LSR type transmission tower?

5331


how to wiring it with contactor and timer together

1767


WHAT IS THE USE OF PIG TAIL IN WINDOW CT ?

2476


Explain what are inter-poles and why they are required in a dc machine.

1039


any body,pls tell me how to done relay coordination ? how to coordinate by TCC curve?how to read the tcc curve?

2080


What is the alternate solution for testing of polarity by using polarity tester while its milli ammeter does not works?

1935


What is the difference between type1 and type2 relay protection co-ordination for motor feeders

2183


what is v/f control in VFD?

1487


what is EIB lighting control system? what is the advantages of this system?

3793


why Lightning arrestor are made by 2 seperate stack of inslutor but why cvt are in single stack of insulator.

1925


What is pi controller?

1134


what is under coal gassification?

2016


Dear all, i completed M.E(Power Electronics & Drives) 2011 passed out having 78% so i need job in core side but i don't know how can i receive the calls from electrical companies and i uploaded my CV in naukri, times jobs etc.. In that iam not recieved any mails from good companies so give me best procedure plzzzzzzzzzzzzzzzzzzzzzzzz..... Thanks, K.Linga Reddy Email-id:-lingareddykmthm@gmail.com Ph no:-08015402078

1757


Define maximum demand?

1011