1) 1 Carpenter + 1 Helper - 5.5 - 6.5 Sqm/Day
2) 1 Steel fitter + 1 Helper - 150 - 200 Kgs/Day (Cut, Bend, Placing)
3) 1 Maon + 1 Helper - 10 Sqm/Day (Blockwork)
4) 1 Mason + 1 Helper - 12 Sqm/Day(wall plastering)
5) 1 Mason + 1 Helper - 10 sqm/Day(Ceiling Plastering)
6) 1 Mason + 1 Helper - 8 Sqm/Day(External Plastering)
7) 1 Tiler + 1 Helper
12 Sqm/Day (Vitrified Tile)
10 Sqm/Day ( Ceramic floor Tile)
8 Sqm/Day ( Ceramic wall Tile)
| Is This Answer Correct ? | 105 Yes | 3 No |
Post New Answer View All Answers
how many re use can use shutting material. timber ? ply? steel? plastic? fibre? aluminium? Doka?
What are the joints wants to made in masonry where door opening, arches like etc..
Time required for curing of wall tiles before fixing
Labor requirement for each item needed? Lean Concrete 103.550m3 Concrete for Foundation and Structure 1753.000m3 Expansion joint 288.000m Contraction joint 127.000m Dowel bar 450.000m
How cracks in concrete can be avoided?
How to calculate volume of concrete & steel on tank foundation & ring wall ?
what is the cost differene of a same structure when it is constructed with brick masonary, and when it is constructed with concrete as a frame structure.????????
What are the RISKS during the project construction?
Design a reinforced concrete combined footing (rectangular) for two columns located 3.60 metres apart. The overall sizes of the columns are 40cm x 40cm and 69cm x 60cm and the loads on them are 1000 kn and 1500 kn respectively. The space available for the width of the footing is restricted to 180cm. The S.B.C. of the soil is 280 kn/mm2 use M15 concrete.
What is the Systematic Responsibility Site Engineer? Who are the above and under co-oridinating ? What is office & Site co-ordination of Site Engineer?
can we use PPC for concrete wall, If yes, what is the concrete (PPC & OPC) grade for Non- load bearing concrete wall, load bearing concrete wall & for cellar retaining wall.
I need Bhel engineertrainy test papers in civil engineering please send to email id - hisandy66@gmail.com
Explain what is zoning permit?
Which is the direction of negative angle?
How does a traffic light signal work ?