1) One mason per day how many cu.m work will do as per list
given a) Brick work,hollow brick work and cc block work and
plastering how many m2 per day 2) one carpenter per day how
many m2 will do as well as scaffolding how many m3
Answer Posted / ramji
One meson one helper 8hours150sq,m plenty plaster
| Is This Answer Correct ? | 1 Yes | 23 No |
Post New Answer View All Answers
residential projects,structural.
Hi.. Can i get hel in finding HPCL previous year question paper? plz help me in finding thiss..
trapozidal
how clculate excavated or backfilling quantity by simpson's rule
how can we calculate steel value, depending on load
You have 3 snd sample of different FM=0.21,FM=0.95,FM=2.90 which one is suitable for a)plastering on R.C.C b)plastering on masonary wall c)concreting column d)concreting of bored pile.also justify your answer.
i have applied 40mm spacer in the concrete for tie beam. is it correct? kindly give me if there any code available
howto calculate the quantities of material used in fly ash brick after finding the volume??
how water proof chemicals act in concrete to avoid leek?
beam length 73 feet 4 inch,width 01 feet,height 50 inch so every beam load how much? and what quantity of M.S ROD? both side ony two column in middle no column.pls inform me that this is stable or not ? and how much risk of this beam?
What are the different types of runners?
What is the basic difference between OPC
if dia of inner circle is 42 m and depth is 1.5 m and width is 1 m ,then whait is the quantity of steel?
In jack arch floor, the rise is kept?
what is meant by csr in foundation? what is sbc?what is meant by contour line?