how to calculate rate analysis of M25 grade concrete
Answer Posted / br rijal
Solution/ BR Rijal
Volume of dry concrete = 1.54 to 1.57 times volume of wet concrete
so,
calculation for 1 cu.m of concrete works:-
summation of ratio of concrete M25(1:1:2) = (1+1+2) = 4
Shrinkage Factor = 1.55 ( Assumed)
so,
Total volume of wet concrete required = 1.55 cu.m
Now,
Volume of cement required = (1/4)* 1.55 = 0.388 cu.m
= (0.388 / 1440) = 558 kg
cement required = (558 / 50) = 11.16 bags
volume of sand required = (1/4) * 1.55 = 0.388 cu.m
volume of Aggregate required = (2/4) * 1.55 = 0.775 cu.m
Therefore, For 1 cu.m of M25(1:1:2) concrete works;
cement required = 11.16 bags
sand required = 0.388 cu.m
Aggregate required = 0.775 cu.m
Is This Answer Correct ? | 3 Yes | 2 No |
Post New Answer View All Answers
IS THERE ANY JOBS FOR THOSE WHO ARE IN FINAL YAER OF ENGINEERING(CIVIL) IN MUMBAI
What is a projection line?
How to cal. The weight of hollow pipe?
What is the difference between the concrete mix design carried out by IS10262 and by ACI method ?
how i get all type of short type question answer about civil engg
How to calculate plastering for elevated water storage tank
how i can calculate the actual nos & size of steel to make 1000sqft. x 3"thick slab
i have boiler of 35 tone and wanted dig out foundation is there any body to help me to carry out calculation for the foundation like
what is the difference between tsp & tower
what is the clear cover for shearwall?
How to calculate unit weight of concrete for m40 grade.
cause of cylinder test failure
sir tell me the formula for calculating the volume of 380mm dia double under reamed pile of 4.0 mts depth.
Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?
Exterior Joints,define