how to calculate rate analysis of M25 grade concrete
Answer Posted / br rijal
Solution/ BR Rijal
Volume of dry concrete = 1.54 to 1.57 times volume of wet concrete
so,
calculation for 1 cu.m of concrete works:-
summation of ratio of concrete M25(1:1:2) = (1+1+2) = 4
Shrinkage Factor = 1.55 ( Assumed)
so,
Total volume of wet concrete required = 1.55 cu.m
Now,
Volume of cement required = (1/4)* 1.55 = 0.388 cu.m
= (0.388 / 1440) = 558 kg
cement required = (558 / 50) = 11.16 bags
volume of sand required = (1/4) * 1.55 = 0.388 cu.m
volume of Aggregate required = (2/4) * 1.55 = 0.775 cu.m
Therefore, For 1 cu.m of M25(1:1:2) concrete works;
cement required = 11.16 bags
sand required = 0.388 cu.m
Aggregate required = 0.775 cu.m
Is This Answer Correct ? | 3 Yes | 2 No |
Post New Answer View All Answers
design the irrigation canal(b,B,h )head is 3tms of water is supplied to the 200hectars of area and the base period crop is 150days dance to water travels as 35km.the canal section is trapezoidal and also calculate the slop the canal
what is the types of door's wood?
How to calculate woden area in sft and Cft
Dear Sir, I work in hydro project. I want to hire Scorpio/ Bolero on monthly basis. But how can i justified its amount (Hourly basic). Please solve my problem
What is the cemnent ratio
how to calculate detail quantity of bricks and mortar for 500 cu.ft masonry work. consider wall thickness 9 inches
4. Differentiate between NC and OC soils. Draw curves for (i) Stress vs Strain (ii) Volume charge vs Strain (iii) Pore pressure vs Strain for these soils
What is the difference between Grade I, II and III of GSB?
Curing time for 1)R.C.C slab 2)B.W 3)Plastering
How many feet are in 4 square yards?
how beam.coloum ,slab, footing are designed as per indian code.. detail procedure?
can you provide a link for manual design of building?
asubmerged weir is one in which the water level on the down stream side of the weir is just at the crest level below the crest level above the crest level at stamp elevation as water surface on upstream
what is c4x light weight cement blocks
What is critical path method (c.p.m)?