how much quantity a carpenter do shuttering per day

Answer Posted / m md ali

Formwork-Footings, foundations, ground- Sqm 8
Formwork-Columns, pedestals- Sqm 6
Formwork-Beams and slabs -Sqm 8
Formwork-Tie beams, arches, lintels.
Formwork-Walls- Sqm 12
Formwork-Circular, special shapes -Sqm 4
Formwork- Making timber shutters -Sqm 8

Is This Answer Correct ?    30 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are your future hopes for this job?

1831


Explain why concrete barriers have curved surface profiles?

819


why we provide bent up reinforcement bars at l/4 ? if it is because of diagonal shear , how does it acts ?

2581


What is the mix propotion of M10,M15,M20,M25,M30,M40,M50.M60 cement content,aggrigate,sand and water ratio.

4211


if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.

1668






How many litres of water used for curing of 1000sqft of slav

1018


sir tell me the formula for calculating the volume of 380mm dia double under reamed pile of 4.0 mts depth.

1489


what are the strength theories for yeilding and fracture materials. state the theory more suited for 1. mild steel or 2. concrete

3526


what is raft foundation

1132


What are the important hardware systems used for cad?

672


How much of fly ash is allowable in Portland cement and what is the disadvantage when the level of fly ash is increased?

1365


Hi my name is Binyam and I'm a 7th grader at Mayfield Woods Middle school. I decided to research civil engineering as my career and i need to know a few thing about your profession. What is your daily routine? What are some advantages and things you like about your job? What are some disadvantages What is the hardest thing you have done? What education have you gone through to become a civil engineer? How long is your work day? What is your work environment like? What is your salary? What made you want to become an engineer? What tools do you you use? Thank you for answering my questions

1809


In earth work 1300 cum soil how to calculate how many liters require in water

1999


hi, i am doing my B.tech third year and i want to have a job in Genpact...So can you help me which kind of job would be more appropriate for me in such a company and How should i prepare for an interview?

1953


what might be the problem faced in the near future if the M-sand is used in the place of river sand during wall plastering? (As per IS)

1518