how much quantity a carpenter do shuttering per day
Answer Posted / m md ali
Formwork-Footings, foundations, ground- Sqm 8
Formwork-Columns, pedestals- Sqm 6
Formwork-Beams and slabs -Sqm 8
Formwork-Tie beams, arches, lintels.
Formwork-Walls- Sqm 12
Formwork-Circular, special shapes -Sqm 4
Formwork- Making timber shutters -Sqm 8
| Is This Answer Correct ? | 31 Yes | 3 No |
Post New Answer View All Answers
can any one give me sample question paper of BHEL at mdansari86@gmail.com as i m appearing for the same exam.
why we create short columns under grade slab?
WET BULB TEMPERATURE AND DRY BULB TEMPERATURE?
What is different between DI Pipe and CI pipe?
what are the changes in concrete pour height as per IS 456, 2009?
What are the techniques to measure road difference?
How to find coloumn vertical cut length floor to floor & lap + bend or anything plz clearfiy
what is the quantity of block work required to construct a compound wall of 6" thick,and 212 lenght
how much of the strength comes from post-production curing
if 20mm aggregate is coming by weight 25 ton in a 10 wheeler hywa ,then what will be total volume of aggregate in cubic feet.
What is bylayer?
How to calculate woden area in sft and Cft
Why are separation membranes used between concrete pavement slab and sub-base?
why is M25 and Fe 500 assumed to be most economical? i feel it is not.This is because higher grade of concrete and steel has higher lapping length and anchorage length compared to lower grades..
how much used soil in 1 brick of standard size?