How to calculate the no of bags required for 12mm thick 1:6
plastering?
Answer Posted / ashok yadav
Take 100 Sqm 12 mm thick plaster in Cement mortar 1:6 on Brick work
Volume of mortar = 100x0.012 = 1.20 Cum
Add 25% for dubbing and wastage= 0.30 Cum
Total (dry mortar) = 1.50 Cum
Add 30% dry to wet mortar = 0.45 Cum
Total (wet mortar) = 1.95 Cum
Cement = 1.95/7 = 0.279 Cum
= 0.279x28.8 =8.03 Bags
Sand = 0.279x6 = 1.67 Cum
| Is This Answer Correct ? | 0 Yes | 2 No |
Post New Answer View All Answers
the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum
1.Why we are preferring 43 grade cement than 53 grade cement. 2. Approximate cost difference between 43 and 53 grade cement. Thanks.
Please tell me the quantity of cement, sand, flyash, foaming agent required for 1 cubic meter of cellular lightweight concrete blocks. also , is there any admixtures required for the CLC blocks production.
How we calculate the service time of buildings
Explain the term 'Gross unit rate' and identify the items that may be included in the gross unit rate.
Define What is unit weight of normal concrete?
for Precast foundation howmany days required we can shift the foundation with american Standards i need reference with section any body can help
Hi my name is Binyam and I'm a 7th grader at Mayfield Woods Middle school. I decided to research civil engineering as my career and i need to know a few thing about your profession. What is your daily routine? What are some advantages and things you like about your job? What are some disadvantages What is the hardest thing you have done? What education have you gone through to become a civil engineer? How long is your work day? What is your work environment like? What is your salary? What made you want to become an engineer? What tools do you you use? Thank you for answering my questions
The building has 12 columns of 12x9 in 3 rows of 4 each in a plot of 50'x30', The central row is strengthened with 16mm twisted rods. The roof area is 1500 sft including balconies. calculate the load factor per sft. Also indicate the number of roofs the building can withstand.
What are the main reasons for conducting pull-out tests for soil nails?
primary treatment of sewagw consist of removal of floating materials removal of sand & grit removal of organic materials all above
How to calculate unit weight of concrete for m40 grade.
how much one carpenter can doing shuttering of slab in one day
what are the five benefits of using standard terminology in the measurement process?
what are the values of compressieve strenght?